Large-span arc-shaped modeling suspended ceiling construction method
The invention relates to the technical field of arc-shaped suspended ceiling construction, and particularly discloses a large-span arc-shaped modeling suspended ceiling construction method. The large-span arc-shaped modeling suspended ceiling construction method specifically comprises the following steps that S1, indoor scanning is carried out, and a three-dimensional model is established; S2, according to the three-dimensional model and the indoor actual situation, a suspended ceiling joist is divided into a plurality of ceiling joist units; S3, scaffolds are erected on a construction site, ceiling construction paying-off is carried out, and a supporting frame and the ceiling joist units are mounted in sequence; S4, a silicon ceramic composite board is mounted; S5, putty construction is carried out; and S6, veneer bamboo skin is pasted, and construction is completed. The suspended ceiling joist is divided into the multiple suspended ceiling joist units, and the suspended ceiling joist is mounted in a modularized mode, so that the high-altitude operation time is shortened, the construction efficiency is improved, the labor cost is reduced, and the construction period is shortened.
本发明涉及弧形吊顶施工技术领域,具体公开了一种大跨度弧形造型吊顶施工方法,具体包括以下步骤:步骤S1:对室内扫描,建立三维模型;步骤S2:根据三维模型和室内实际情况,分割为多个吊顶龙骨单元;步骤S3:施工现场脚手架搭设,吊顶施工放线;依次支撑架安装、吊顶龙骨单元安装;步骤S4:安装硅陶复合板;步骤S5:腻子施工;步骤S6:贴饰面竹皮,完成施工。采用将吊顶龙骨分割为多个吊顶龙骨单元,通过将吊顶龙骨模块化安装,减少了高空作业时间,加快了施工效率,降低了人工成本,节约了施工工期。
Large-span arc-shaped modeling suspended ceiling construction method
The invention relates to the technical field of arc-shaped suspended ceiling construction, and particularly discloses a large-span arc-shaped modeling suspended ceiling construction method. The large-span arc-shaped modeling suspended ceiling construction method specifically comprises the following steps that S1, indoor scanning is carried out, and a three-dimensional model is established; S2, according to the three-dimensional model and the indoor actual situation, a suspended ceiling joist is divided into a plurality of ceiling joist units; S3, scaffolds are erected on a construction site, ceiling construction paying-off is carried out, and a supporting frame and the ceiling joist units are mounted in sequence; S4, a silicon ceramic composite board is mounted; S5, putty construction is carried out; and S6, veneer bamboo skin is pasted, and construction is completed. The suspended ceiling joist is divided into the multiple suspended ceiling joist units, and the suspended ceiling joist is mounted in a modularized mode, so that the high-altitude operation time is shortened, the construction efficiency is improved, the labor cost is reduced, and the construction period is shortened.
本发明涉及弧形吊顶施工技术领域,具体公开了一种大跨度弧形造型吊顶施工方法,具体包括以下步骤:步骤S1:对室内扫描,建立三维模型;步骤S2:根据三维模型和室内实际情况,分割为多个吊顶龙骨单元;步骤S3:施工现场脚手架搭设,吊顶施工放线;依次支撑架安装、吊顶龙骨单元安装;步骤S4:安装硅陶复合板;步骤S5:腻子施工;步骤S6:贴饰面竹皮,完成施工。采用将吊顶龙骨分割为多个吊顶龙骨单元,通过将吊顶龙骨模块化安装,减少了高空作业时间,加快了施工效率,降低了人工成本,节约了施工工期。
Large-span arc-shaped modeling suspended ceiling construction method
一种大跨度弧形造型吊顶施工方法
ZHAO HENG (author) / LUO LIFU (author) / LI QIBING (author) / ZHAO KAINAN (author)
2021-11-02
Patent
Electronic Resource
Chinese
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
European Patent Office | 2015
|Large-span arc-shaped suspended ceiling structure and construction method thereof
European Patent Office | 2024
|Large-span arc-shaped suspended ceiling for subway station
European Patent Office | 2024
|European Patent Office | 2023
|Construction method of large-span steel beam roof suspended ceiling conversion layer
European Patent Office | 2023
|