Fabricated subway station construction method
The invention provides a fabricated subway station construction method. The fabricated subway station construction method comprises the steps that a foundation pit is excavated; bottom-layer assemblies are assembled, and when the bottom-layer assemblies with the preset ring number are assembled, middle-layer assemblies are assembled on the bottom-layer assemblies; and when the assembly of the middle-layer assemblies with the preset ring number is completed, the assembly of top-layer assemblies on the middle-layer assemblies is started. Compared with the prior art, the assembly of the middle-layer assemblies can be started after the bottom-layer assemblies are assembled to the preset ring number, then the assembly of the top-layer assemblies is started after the middle-layer assemblies are assembled to the preset ring number, then the bottom-layer assemblies, the middle-layer assemblies and the top-layer assemblies are assembled at the same time in a stepped mode, until all the bottom-layer assemblies, the middle-layer assemblies and the top-layer assemblies are assembled, a subway station is formed, the assembling efficiency is improved, and the construction period is shortened.
本发明提供了一种装配式地铁车站施工方法,包括:开挖基坑;装配底层组件,当完成预定环数的所述底层组件装配时,开始在所述底层组件上进行中层组件的装配;当完成预定环数的中层组件装配时,开始在所述中层组件上进行顶层组件的装配。相对于现有技术,本发明可以在底层组件装配至预定环数后开始中层组件的装配,接着在中层组件装配至预定环数后开始顶层组件的装配,之后底层组件、中层组件和顶层组件呈阶梯式同时进行装配,直至将所有底层组件、中层组件和顶层组件全部装配完成以形成地铁车站,提高了装配的效率,缩短了工期。
Fabricated subway station construction method
The invention provides a fabricated subway station construction method. The fabricated subway station construction method comprises the steps that a foundation pit is excavated; bottom-layer assemblies are assembled, and when the bottom-layer assemblies with the preset ring number are assembled, middle-layer assemblies are assembled on the bottom-layer assemblies; and when the assembly of the middle-layer assemblies with the preset ring number is completed, the assembly of top-layer assemblies on the middle-layer assemblies is started. Compared with the prior art, the assembly of the middle-layer assemblies can be started after the bottom-layer assemblies are assembled to the preset ring number, then the assembly of the top-layer assemblies is started after the middle-layer assemblies are assembled to the preset ring number, then the bottom-layer assemblies, the middle-layer assemblies and the top-layer assemblies are assembled at the same time in a stepped mode, until all the bottom-layer assemblies, the middle-layer assemblies and the top-layer assemblies are assembled, a subway station is formed, the assembling efficiency is improved, and the construction period is shortened.
本发明提供了一种装配式地铁车站施工方法,包括:开挖基坑;装配底层组件,当完成预定环数的所述底层组件装配时,开始在所述底层组件上进行中层组件的装配;当完成预定环数的中层组件装配时,开始在所述中层组件上进行顶层组件的装配。相对于现有技术,本发明可以在底层组件装配至预定环数后开始中层组件的装配,接着在中层组件装配至预定环数后开始顶层组件的装配,之后底层组件、中层组件和顶层组件呈阶梯式同时进行装配,直至将所有底层组件、中层组件和顶层组件全部装配完成以形成地铁车站,提高了装配的效率,缩短了工期。
Fabricated subway station construction method
一种装配式地铁车站施工方法
LUO PU (author) / HUANG CHAO (author) / ZHANG ZHUN (author) / MA WENBIN (author) / CHENG FENG (author) / SHU JUN (author) / RAO LANG (author) / ZHENG ZENG (author) / CHEN YAOXUE (author) / LI NAN (author)
2021-11-09
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method of fabricated subway station and fabricated subway station
European Patent Office | 2024
|Fabricated subway station waterproof system construction method
European Patent Office | 2024
|FABRICATED SUBWAY STATION AND CONSTRUCTION METHOD THEREFOR
European Patent Office | 2022
|Fabricated subway station and construction method thereof
European Patent Office | 2023
|