A platform for research: civil engineering, architecture and urbanism
Dust prevention and noise reduction process for cast-in-situ bored pile construction
The invention discloses a dust prevention and noise reduction process for cast-in-situ bored pile construction. The dust prevention and noise reduction process comprises a field plane management measure, cast-in-situ bored pile construction, a field noise prevention measure and a construction dust prevention measure, the field noise prevention measure comprises regular maintenance of field equipment, low-noise construction mechanical equipment is adopted, the construction machinery should meet the environmental protection standard, the construction dust prevention measures comprise non-overload closed transportation of a transportation machine in the transportation process of loose particles such as cement and gravel, anti-flying measures on site cement and river sand, watering dust falling on a construction site regularly every day, stacking of building materials in a designated area, and centralized stacking treatment of garbage. According to the dust prevention and noise reduction process, noise generated on the construction site of a cast-in-situ bored pile is reduced through the field noise prevention measure, dust generated on the construction site of the cast-in-situ bored pile is reduced through the construction dust prevention measure, the safety of constructors in the construction process is guaranteed, and the surrounding environment is protected.
本发明公开了一种钻孔灌注桩施工防尘降噪工艺,包括现场平面管理措施、钻孔灌注桩施工、现场防噪措施和施工防尘措施,其中现场防噪措施包括对现场设备进行定期维护和保养,采用低噪音施工机械设备,施工机械应符合环保标准,施工防尘措施包括对于水泥和砂砾这种松散颗粒运输过程运输机械不超载封闭运输,对现场的水泥和河砂采取防飞扬措施,每天定时对施工现场进行洒水降尘,建筑材料应该堆放在指定区域,垃圾要集中堆放处理。本发明通过现场防噪措施减小钻孔灌注桩施工现场产生的噪声,施工防尘措施减少钻孔灌注桩施工现场产生的灰尘,保证施工人员施工过程中的安全性,以及保护周围环境。
Dust prevention and noise reduction process for cast-in-situ bored pile construction
The invention discloses a dust prevention and noise reduction process for cast-in-situ bored pile construction. The dust prevention and noise reduction process comprises a field plane management measure, cast-in-situ bored pile construction, a field noise prevention measure and a construction dust prevention measure, the field noise prevention measure comprises regular maintenance of field equipment, low-noise construction mechanical equipment is adopted, the construction machinery should meet the environmental protection standard, the construction dust prevention measures comprise non-overload closed transportation of a transportation machine in the transportation process of loose particles such as cement and gravel, anti-flying measures on site cement and river sand, watering dust falling on a construction site regularly every day, stacking of building materials in a designated area, and centralized stacking treatment of garbage. According to the dust prevention and noise reduction process, noise generated on the construction site of a cast-in-situ bored pile is reduced through the field noise prevention measure, dust generated on the construction site of the cast-in-situ bored pile is reduced through the construction dust prevention measure, the safety of constructors in the construction process is guaranteed, and the surrounding environment is protected.
本发明公开了一种钻孔灌注桩施工防尘降噪工艺,包括现场平面管理措施、钻孔灌注桩施工、现场防噪措施和施工防尘措施,其中现场防噪措施包括对现场设备进行定期维护和保养,采用低噪音施工机械设备,施工机械应符合环保标准,施工防尘措施包括对于水泥和砂砾这种松散颗粒运输过程运输机械不超载封闭运输,对现场的水泥和河砂采取防飞扬措施,每天定时对施工现场进行洒水降尘,建筑材料应该堆放在指定区域,垃圾要集中堆放处理。本发明通过现场防噪措施减小钻孔灌注桩施工现场产生的噪声,施工防尘措施减少钻孔灌注桩施工现场产生的灰尘,保证施工人员施工过程中的安全性,以及保护周围环境。
Dust prevention and noise reduction process for cast-in-situ bored pile construction
一种钻孔灌注桩施工防尘降噪工艺
HUANG DENGQI (author)
2021-11-19
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pile foundation construction process of cast-in-situ bored pile
European Patent Office | 2024
|Pile foundation construction process of cast-in-situ bored pile
European Patent Office | 2023
|