A platform for research: civil engineering, architecture and urbanism
Dry hanging hook and dry hanging construction process
The invention discloses a dry hanging hook and a dry hanging construction process. The dry hanging hook is sequentially provided with a clamping hook part connected with a horizontal keel in a clamped mode, a back face supporting part used for supporting the back faces of upper-layer wall bricks, a bottom face supporting part used for supporting the bottom faces of upper-layer wall bricks, a lower abutting part used for abutting against a lower-layer wall brick towards a wall body side, and an upper abutting part used for abutting against the upper-layer wall brick towards the wall body side. According to the dry hanging hook, the gravity of the wall bricks is ingeniously utilized, the bottom face supporting part, the lower abutting part and the upper abutting part are pressed and positioned in a linkage mode, and positioning and fixing of the upper-layer wall bricks and the lower-layer wall bricks are achieved. Besides, the mounting structure of the dry hanging hook enables an external wall tile to have a tiny inclined surface, so that rainwater is ingeniously prevented from immersing into the back face of the wall tile, and the problem of water bleeding and shadow is greatly improved. According to the dry hanging construction process, only the installation position of the horizontal keel is required, when the wall bricks are laid, adjustment and installation of hanging pieces do not need to be considered, gluing and fixing are not needed either, therefore, the construction efficiency is greatly improved, the material cost and the construction amount are reduced exponentially, and the huge superiority is achieved.
一种干挂钩,依次具有与水平龙骨卡接的卡钩部、用于支撑上层墙砖背面的背面支撑部、用于支撑上层墙砖底面的底面支撑部、用于向墙体侧抵压下层墙砖的下抵压部、用于向墙体侧抵压上层墙砖的上抵压部。本干挂钩巧妙地利用墙砖的重力,使底面支撑部、下抵压部和上抵压部得到联动的压紧和定位,实现了对上下层墙砖的定位和固定。此外,干挂钩的安装结构使外墙砖具有微小的倾斜面,巧妙地避免了雨水对墙砖背面的浸入,使水洇阴影问题得到了大幅改善。一种干挂施工工艺,仅对水平龙骨的安装位置有要求,在铺设墙砖时,不用考虑挂件的调节和安装问题,也不需要施胶固定,施工效率因此得到大幅提高,成倍地减少了材料成本和施工量,具有巨大的优越性。
Dry hanging hook and dry hanging construction process
The invention discloses a dry hanging hook and a dry hanging construction process. The dry hanging hook is sequentially provided with a clamping hook part connected with a horizontal keel in a clamped mode, a back face supporting part used for supporting the back faces of upper-layer wall bricks, a bottom face supporting part used for supporting the bottom faces of upper-layer wall bricks, a lower abutting part used for abutting against a lower-layer wall brick towards a wall body side, and an upper abutting part used for abutting against the upper-layer wall brick towards the wall body side. According to the dry hanging hook, the gravity of the wall bricks is ingeniously utilized, the bottom face supporting part, the lower abutting part and the upper abutting part are pressed and positioned in a linkage mode, and positioning and fixing of the upper-layer wall bricks and the lower-layer wall bricks are achieved. Besides, the mounting structure of the dry hanging hook enables an external wall tile to have a tiny inclined surface, so that rainwater is ingeniously prevented from immersing into the back face of the wall tile, and the problem of water bleeding and shadow is greatly improved. According to the dry hanging construction process, only the installation position of the horizontal keel is required, when the wall bricks are laid, adjustment and installation of hanging pieces do not need to be considered, gluing and fixing are not needed either, therefore, the construction efficiency is greatly improved, the material cost and the construction amount are reduced exponentially, and the huge superiority is achieved.
一种干挂钩,依次具有与水平龙骨卡接的卡钩部、用于支撑上层墙砖背面的背面支撑部、用于支撑上层墙砖底面的底面支撑部、用于向墙体侧抵压下层墙砖的下抵压部、用于向墙体侧抵压上层墙砖的上抵压部。本干挂钩巧妙地利用墙砖的重力,使底面支撑部、下抵压部和上抵压部得到联动的压紧和定位,实现了对上下层墙砖的定位和固定。此外,干挂钩的安装结构使外墙砖具有微小的倾斜面,巧妙地避免了雨水对墙砖背面的浸入,使水洇阴影问题得到了大幅改善。一种干挂施工工艺,仅对水平龙骨的安装位置有要求,在铺设墙砖时,不用考虑挂件的调节和安装问题,也不需要施胶固定,施工效率因此得到大幅提高,成倍地减少了材料成本和施工量,具有巨大的优越性。
Dry hanging hook and dry hanging construction process
一种干挂钩及干挂施工工艺
GAO SHUIWANG (author) / GAO SHUNWANG (author) / WANG ZHUO (author) / YANG YONG (author) / GAO ZHE (author) / GAO HE (author) / GAO YANFENG (author)
2021-12-03
Patent
Electronic Resource
Chinese
IPC:
E04F
FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
,
Ausbau von Bauwerken, z.B. Treppen, Fußböden