Railway tunnel base defect anchoring, injecting and draining integrated treatment method
The invention provides a railway tunnel base defect anchoring, injecting and draining integrated treatment method. The method comprises the following steps that a plurality of glue injecting holes are drilled in the tunnel bottom of a tunnel base defect section, and grouting anchor piles are arranged in the glue injecting holes, so that the grouting anchor piles and a tunnel base structure are anchored, and base anchoring construction is completed; glue injecting equipment is arranged and communicates with the grouting anchor piles to conduct glue injecting construction on the tunnel base, so that grouting materials are injected into gaps of the tunnel base, and base glue injecting construction is completed; and a flow guiding and draining system is arranged between a railway sleeper and base rock and communicates with drainage ditches on the two sides of the bottom of a tunnel.
本发明提出了一种铁路隧道基底病害锚注排一体化的整治方法,包括以下步骤:在隧道基底病害区段的隧底钻设多个注胶孔,并在所述注胶孔内布设注浆锚桩,以使所述注浆锚桩与隧道基底结构形成锚固,从而完成基底锚固施工;布设注胶设备,并将所述注胶设备与所述注浆锚桩连通以对隧道基底进行注胶施工,以向隧道基底的缝隙内注入注浆材料,从而完成基底注胶施工;在铁路轨枕与基岩之间布设导流排水系统,且使所述导流排水系统与隧道底部两侧的排水沟连通。
Railway tunnel base defect anchoring, injecting and draining integrated treatment method
The invention provides a railway tunnel base defect anchoring, injecting and draining integrated treatment method. The method comprises the following steps that a plurality of glue injecting holes are drilled in the tunnel bottom of a tunnel base defect section, and grouting anchor piles are arranged in the glue injecting holes, so that the grouting anchor piles and a tunnel base structure are anchored, and base anchoring construction is completed; glue injecting equipment is arranged and communicates with the grouting anchor piles to conduct glue injecting construction on the tunnel base, so that grouting materials are injected into gaps of the tunnel base, and base glue injecting construction is completed; and a flow guiding and draining system is arranged between a railway sleeper and base rock and communicates with drainage ditches on the two sides of the bottom of a tunnel.
本发明提出了一种铁路隧道基底病害锚注排一体化的整治方法,包括以下步骤:在隧道基底病害区段的隧底钻设多个注胶孔,并在所述注胶孔内布设注浆锚桩,以使所述注浆锚桩与隧道基底结构形成锚固,从而完成基底锚固施工;布设注胶设备,并将所述注胶设备与所述注浆锚桩连通以对隧道基底进行注胶施工,以向隧道基底的缝隙内注入注浆材料,从而完成基底注胶施工;在铁路轨枕与基岩之间布设导流排水系统,且使所述导流排水系统与隧道底部两侧的排水沟连通。
Railway tunnel base defect anchoring, injecting and draining integrated treatment method
一种铁路隧道基底病害锚注排一体化的整治方法
MA WEIBIN (author) / GUO XIAOXIONG (author) / NIU YABIN (author) / CHAI JINFEI (author) / XU JIANWEI (author) / ZHANG BO (author) / FU BINGXIAN (author) / MA CHAOFENG (author) / ZHAO PENG (author) / LI YAO (author)
2021-12-07
Patent
Electronic Resource
Chinese
IPC:
E21F
Sicherheitsvorrichtungen, Förderung, Auffüllen oder Bergversatz, Rettungswesen, Bewetterung oder Entwässerung in oder von Gruben oder Tunnels
,
SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINAGE IN OR OF MINES OR TUNNELS
/
E02D
FOUNDATIONS
,
Gründungen
/
E21D
SHAFTS
,
Schächte
Bolting-grouting integrated treatment method for railway tunnel base disease
European Patent Office | 2015
|Anchoring and draining underground steam lines
Engineering Index Backfile | 1928
|The Lötschberg Railway Base Tunnel
Online Contents | 1997
|Sediment-preventing platform pile shoe capable of automatically injecting water and draining water
European Patent Office | 2022
|The Loetschberg Railway Base Tunnel
British Library Online Contents | 1997
|