A platform for research: civil engineering, architecture and urbanism
Construction method of fabricated frame structure
The invention relates to the technical field of constructional engineering, in particular to a construction method of a fabricated frame structure. The construction method of the fabricated frame structure comprises the following steps that a vertical prefabricated part is installed on a to-be-constructed plate, and the vertical prefabricated part is provided with a cast-in-place cavity; a prefabricated beam is installed above the to-be-constructed plate; a prefabricated plate is installed above the to-be-constructed plate, the prefabricated plate comprises a steel pipe truss, and part of the prefabricated plate is located above the vertical prefabricated part and the prefabricated beam; and concrete is poured in a cast-in-place concrete area to form a frame structure. According to the construction method of the fabricated frame structure, the vertical prefabricated part, the prefabricated beam and the prefabricated plate are produced by adopting automatic production equipment in a factory in advance, during site construction, the hoisting effect is high, the construction speed is high, the construction time can be greatly shortened, the construction efficiency can be improved, and the construction cost can be reduced.
本发明涉及建筑工程技术领域,具体涉及一种装配式框架结构的施工方法。装配式框架结构的施工方法包括以下步骤:在待施工板上安装竖向预制构件,其中,竖向预制构件具有现浇空腔;在待施工板的上方安装预制梁;在待施工板的上方安装预制板,其中,预制板包括钢管桁架,预制板的部分位于竖向预制构件和预制梁的上方;在现浇混凝区域浇筑混凝土,以形成框架结构。本发明的竖向预制构件、预制梁及预制板提前在工厂采用自动化生产设备生产,在现场施工时,吊装效果高,施工速度快,可以大大缩短施工时间,提高施工效率,降低施工成本。
Construction method of fabricated frame structure
The invention relates to the technical field of constructional engineering, in particular to a construction method of a fabricated frame structure. The construction method of the fabricated frame structure comprises the following steps that a vertical prefabricated part is installed on a to-be-constructed plate, and the vertical prefabricated part is provided with a cast-in-place cavity; a prefabricated beam is installed above the to-be-constructed plate; a prefabricated plate is installed above the to-be-constructed plate, the prefabricated plate comprises a steel pipe truss, and part of the prefabricated plate is located above the vertical prefabricated part and the prefabricated beam; and concrete is poured in a cast-in-place concrete area to form a frame structure. According to the construction method of the fabricated frame structure, the vertical prefabricated part, the prefabricated beam and the prefabricated plate are produced by adopting automatic production equipment in a factory in advance, during site construction, the hoisting effect is high, the construction speed is high, the construction time can be greatly shortened, the construction efficiency can be improved, and the construction cost can be reduced.
本发明涉及建筑工程技术领域,具体涉及一种装配式框架结构的施工方法。装配式框架结构的施工方法包括以下步骤:在待施工板上安装竖向预制构件,其中,竖向预制构件具有现浇空腔;在待施工板的上方安装预制梁;在待施工板的上方安装预制板,其中,预制板包括钢管桁架,预制板的部分位于竖向预制构件和预制梁的上方;在现浇混凝区域浇筑混凝土,以形成框架结构。本发明的竖向预制构件、预制梁及预制板提前在工厂采用自动化生产设备生产,在现场施工时,吊装效果高,施工速度快,可以大大缩短施工时间,提高施工效率,降低施工成本。
Construction method of fabricated frame structure
装配式框架结构的施工方法
MA RONGQUAN (author) / ZHANG BO (author) / LI TAO (author) / ZHANG SHUHUI (author) / XU SHENGJIE (author) / JIN JUDONG (author) / ZHANG BUTING (author)
2021-12-21
Patent
Electronic Resource
Chinese
Rapid construction method for fabricated frame structure
European Patent Office | 2023
|Fabricated frame structure and construction method thereof
European Patent Office | 2024
|Fabricated building frame structure and construction method
European Patent Office | 2024
|Fabricated concrete frame beam structure and construction method
European Patent Office | 2024
|