A platform for research: civil engineering, architecture and urbanism
Steel column mounting process
The invention discloses a steel column installation process which comprises the steps of surveying and setting out, hoisting preparation, temporary facility installation, steel column hoisting and butt joint, steel column position correction and welding and fixing. The steel column installation process has the beneficial effects that the steel ladder is connected with the steel column in a binding mode, the safety ring for pulling the safety rope is welded to one side of the steel ladder, the steel ladder is arranged so that an operator can conveniently remove the lifting rope for lifting the steel column, the steel ladder can be prevented from floating, potential safety hazards are avoided, and the safety of the operator executing the next procedure is guaranteed; the lower plate face of the operation platform is fixedly connected with temporary channel steel welded to the position 1.2 m below the top of the steel column body through welding, so that an operator can stand on the operation platform to operate by climbing the steel ladder stand, meanwhile, the stability of the operation platform is high, and potential safety hazards are greatly reduced. And the horizontal adjusting seat and the perpendicularity adjusting seat are arranged, and the jacks for horizontal adjustment and perpendicularity adjustment are placed in the adjusting seats, so that the position correction of the hoisted steel column is realized.
本发明公开了一种钢柱安装工艺,包括测量放线、吊装准备、安装临时设施、钢柱吊装对接、钢柱位置校正、焊接固定。本发明的有益效果是:钢爬梯与钢柱进行捆绑连接,并在钢爬梯的一侧焊接有拉设安全绳的安全环,设置钢爬梯以便于操作人员摘除吊装钢柱的吊绳,并可防止钢爬梯飘动,造成安全隐患,以确保执行下道工序的操作人员的安全;操作平台的下板面通过焊接与钢柱本体柱顶往下1.2米处焊接的临时槽钢进行固定连接,以便于操作人员通过攀爬钢爬梯站立在操作平台上进行操作,同时操作平台稳定性高,积大的降低了安全隐患;设置有水平调节座以及垂直度调节座,且调节座内放置有用于水平调节以及垂直度调节的千斤顶,实现对所吊装钢柱的位置校正。
Steel column mounting process
The invention discloses a steel column installation process which comprises the steps of surveying and setting out, hoisting preparation, temporary facility installation, steel column hoisting and butt joint, steel column position correction and welding and fixing. The steel column installation process has the beneficial effects that the steel ladder is connected with the steel column in a binding mode, the safety ring for pulling the safety rope is welded to one side of the steel ladder, the steel ladder is arranged so that an operator can conveniently remove the lifting rope for lifting the steel column, the steel ladder can be prevented from floating, potential safety hazards are avoided, and the safety of the operator executing the next procedure is guaranteed; the lower plate face of the operation platform is fixedly connected with temporary channel steel welded to the position 1.2 m below the top of the steel column body through welding, so that an operator can stand on the operation platform to operate by climbing the steel ladder stand, meanwhile, the stability of the operation platform is high, and potential safety hazards are greatly reduced. And the horizontal adjusting seat and the perpendicularity adjusting seat are arranged, and the jacks for horizontal adjustment and perpendicularity adjustment are placed in the adjusting seats, so that the position correction of the hoisted steel column is realized.
本发明公开了一种钢柱安装工艺,包括测量放线、吊装准备、安装临时设施、钢柱吊装对接、钢柱位置校正、焊接固定。本发明的有益效果是:钢爬梯与钢柱进行捆绑连接,并在钢爬梯的一侧焊接有拉设安全绳的安全环,设置钢爬梯以便于操作人员摘除吊装钢柱的吊绳,并可防止钢爬梯飘动,造成安全隐患,以确保执行下道工序的操作人员的安全;操作平台的下板面通过焊接与钢柱本体柱顶往下1.2米处焊接的临时槽钢进行固定连接,以便于操作人员通过攀爬钢爬梯站立在操作平台上进行操作,同时操作平台稳定性高,积大的降低了安全隐患;设置有水平调节座以及垂直度调节座,且调节座内放置有用于水平调节以及垂直度调节的千斤顶,实现对所吊装钢柱的位置校正。
Steel column mounting process
一种钢柱安装工艺
MENG KUN (author) / ZHOU HAIYANG (author) / ZHANG JIAJUN (author) / LIN HU (author) / LIU JIE (author)
2022-02-25
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Quickly-mounted steel column mounting structure and mounting process thereof
European Patent Office | 2022
|European Patent Office | 2023
|