Precast pile perpendicularity control device and method
The invention discloses a precast pile perpendicularity control device and method in the technical field of pile sinking construction. The precast pile perpendicularity control device comprises a control unit, a main rod fixedly installed on the ground, a horizontal control unit arranged at the bottom of the main rod, a vertical control unit arranged on the main rod, a measuring and calculating unit arranged in the control unit and an alarm unit arranged at the top of the control unit. According to the precast pile perpendicularity control device and method, the procedures of manual measurement and command in a traditional piling process are avoided, labor and machine investment is reduced, the functions of automatic monitoring and measurement are achieved through a complete set of equipment, and therefore the percent of pass of perpendicularity and piling efficiency are improved, and the production cost is reduced. The safety risk of personnel under the conditions of complex surrounding environment and night construction is reduced, and the production cost and the safety risk of personnel in the production process are effectively reduced.
本发明公开了沉桩施工技术领域的一种预制桩垂直度控制装置及方法。该预制桩垂直度控制装置包括操控单元,固定安装在地面上的主杆,设置在主杆底部的水平控制单元,设置在主杆上的竖直控制单元,设置在操控单元内的测算单元以及设置在操控单元顶部的报警单元。该预制桩垂直度控制装置及方法规避了传统打桩工艺中人工测量、指挥的工序,降低了降低人工与机械投入,通过成套装置实现自动监测与测算的功能,从而提高垂直度的合格率及打桩效率,降低了周边环境复杂及夜间施工情况下和人员的安全风险,有效的降低了生产成本以及生产过程中人员的安全风险。
Precast pile perpendicularity control device and method
The invention discloses a precast pile perpendicularity control device and method in the technical field of pile sinking construction. The precast pile perpendicularity control device comprises a control unit, a main rod fixedly installed on the ground, a horizontal control unit arranged at the bottom of the main rod, a vertical control unit arranged on the main rod, a measuring and calculating unit arranged in the control unit and an alarm unit arranged at the top of the control unit. According to the precast pile perpendicularity control device and method, the procedures of manual measurement and command in a traditional piling process are avoided, labor and machine investment is reduced, the functions of automatic monitoring and measurement are achieved through a complete set of equipment, and therefore the percent of pass of perpendicularity and piling efficiency are improved, and the production cost is reduced. The safety risk of personnel under the conditions of complex surrounding environment and night construction is reduced, and the production cost and the safety risk of personnel in the production process are effectively reduced.
本发明公开了沉桩施工技术领域的一种预制桩垂直度控制装置及方法。该预制桩垂直度控制装置包括操控单元,固定安装在地面上的主杆,设置在主杆底部的水平控制单元,设置在主杆上的竖直控制单元,设置在操控单元内的测算单元以及设置在操控单元顶部的报警单元。该预制桩垂直度控制装置及方法规避了传统打桩工艺中人工测量、指挥的工序,降低了降低人工与机械投入,通过成套装置实现自动监测与测算的功能,从而提高垂直度的合格率及打桩效率,降低了周边环境复杂及夜间施工情况下和人员的安全风险,有效的降低了生产成本以及生产过程中人员的安全风险。
Precast pile perpendicularity control device and method
预制桩垂直度控制装置及方法
WANG XUEMEI (author) / ZHANG ZUOMING (author)
2022-05-13
Patent
Electronic Resource
Chinese
Precast pile construction perpendicularity detection method
European Patent Office | 2023
|Auxiliary device for guaranteeing perpendicularity of precast pile
European Patent Office | 2023
|Detecting method for perpendicularity of uniform-section precast pile
European Patent Office | 2020
|European Patent Office | 2023
|