Large-diameter inspection well drilling pile method construction method
The invention discloses a pile drilling method construction method for a large-diameter inspection well. The method comprises the steps that a drilling machine is adopted for drilling and digging to form a foundation well with the target hole diameter and the target depth; after the drilling machine is withdrawn, a steel casing is installed in the foundation well; slurry in the foundation well is pumped out of the foundation well; and the conical well bottom of the foundation well is filled with block stones in a throwing mode, and cement stone chips are adopted on the upper portion of a formed riprap layer to form a well bottom foundation. According to the method, only drilling for hole forming is needed in construction, the prefabricated inspection well is installed, and the construction time of a single large-diameter inspection well is shortened to one day. The construction only needs to meet the requirement of lifting the pile drilling machine, and particularly, the improved pile drilling machine adopts a crawler-type chassis, so that the space required by operation is further reduced, and the drilling machine is more suitable for narrow road environments. The construction time is greatly shortened, the space needed by construction is reduced, traffic blocking caused by construction is rapidly recovered, and interference of construction on traffic is reduced to the minimum.
本发明公开了一种大直径检查井钻桩法施工方法,该方法包括采用钻机钻挖形成具有目标孔径及目标深度的基础井;所述钻机撤出后将钢护筒安装至所述基础井内;将所述基础井内的泥浆抽吸至所述基础井以外;将所述基础井的锥形井底采用块石抛填并在形成的抛石层上部采用水泥石屑形成井底基础。本申请提供的方法施工仅需钻进成孔、预制检查井安装,单个大直径检查井施工时间缩短至1天。施工仅需满足钻桩机械起架即可,尤其是改进后的钻桩机采用履带式底盘,进一步减小了作业所需空间,更为适应狭窄道路环境。施工时间的大幅度缩短和施工所需空间的减少,实现了因施工导致的交通阻断快速恢复,将施工对交通的干扰降到了最低。
Large-diameter inspection well drilling pile method construction method
The invention discloses a pile drilling method construction method for a large-diameter inspection well. The method comprises the steps that a drilling machine is adopted for drilling and digging to form a foundation well with the target hole diameter and the target depth; after the drilling machine is withdrawn, a steel casing is installed in the foundation well; slurry in the foundation well is pumped out of the foundation well; and the conical well bottom of the foundation well is filled with block stones in a throwing mode, and cement stone chips are adopted on the upper portion of a formed riprap layer to form a well bottom foundation. According to the method, only drilling for hole forming is needed in construction, the prefabricated inspection well is installed, and the construction time of a single large-diameter inspection well is shortened to one day. The construction only needs to meet the requirement of lifting the pile drilling machine, and particularly, the improved pile drilling machine adopts a crawler-type chassis, so that the space required by operation is further reduced, and the drilling machine is more suitable for narrow road environments. The construction time is greatly shortened, the space needed by construction is reduced, traffic blocking caused by construction is rapidly recovered, and interference of construction on traffic is reduced to the minimum.
本发明公开了一种大直径检查井钻桩法施工方法,该方法包括采用钻机钻挖形成具有目标孔径及目标深度的基础井;所述钻机撤出后将钢护筒安装至所述基础井内;将所述基础井内的泥浆抽吸至所述基础井以外;将所述基础井的锥形井底采用块石抛填并在形成的抛石层上部采用水泥石屑形成井底基础。本申请提供的方法施工仅需钻进成孔、预制检查井安装,单个大直径检查井施工时间缩短至1天。施工仅需满足钻桩机械起架即可,尤其是改进后的钻桩机采用履带式底盘,进一步减小了作业所需空间,更为适应狭窄道路环境。施工时间的大幅度缩短和施工所需空间的减少,实现了因施工导致的交通阻断快速恢复,将施工对交通的干扰降到了最低。
Large-diameter inspection well drilling pile method construction method
一种大直径检查井钻桩法施工方法
BAI DONGDONG (author) / CHEN SHANG (author) / XU HAIJIA (author) / JIA HONGYI (author) / WEI JIANJUN (author)
2022-06-07
Patent
Electronic Resource
Chinese
Construction method for ultra-long large-diameter drilling pouring pile
European Patent Office | 2020
|WELL DRILLING METHOD, CONSTRUCTION METHOD AND WELL CONSTRUCTION PILE
European Patent Office | 2022
|OFFSHORE ROCK-DRILLING REDRIVING-TYPE LARGE-DIAMETER PILE STRUCTURE AND CONSTRUCTION METHOD
European Patent Office | 2018
|Construction method of double-guide-pipe pouring large-diameter drilling hollow pile
European Patent Office | 2024
|Large diameter waterjet ground drilling machine and pile construction method using it
European Patent Office | 2018
|