High-rise building bay window aluminum alloy formwork mounting and reinforcing method
The invention discloses a mounting and reinforcing method for a bay window aluminum alloy formwork of a high-rise building, and belongs to the field of house construction engineering. The floating plate specifically comprises a floating plate cover plate, a floating plate bottom plate, a supporting rod, an early-dismantling head, an anti-floating back ridge, a long opposite-pull rod, a K plate, an embedded bolt, a short wall plate, a corner plate, a short opposite-pull rod, an angle plate, a gasket and an edge sealing plate. According to the method for installing and reinforcing the bay window aluminum alloy formwork of the high-rise building, the bolt holes are reserved in the lower-layer beam in advance, when the upper-layer formwork is erected, the K plate is fixed through the embedded bolts, the fixation of the K plate can effectively support a low wall plate on the upper portion, the formwork on the upper portion cannot fall off or displace, the effect of supporting the aluminum formwork on the upper portion is achieved, and the construction period is shortened. And the perpendicularity can be effectively controlled, and concrete slab staggering is avoided.
本发明公开了一种高层建筑飘窗铝合金模板安装加固方法,属于房屋建设工程领域。具体包括以下:飘板盖板、飘板底板、支撑杆、早拆头、抗上浮背楞、长对拉杆、K板、预埋螺栓、矮墙板、转角板、短对拉杆、角板、垫片、封边板。本发明的一种高层建筑飘窗铝合金模板安装加固方法,提前在下层梁内预留的螺栓孔,在支设上层模板时,采用预埋螺栓将K板固定,K板的固定能有效支撑上部的矮墙板,使上部的模板不会发生掉落及位移,达到支撑上部铝模板的作用,并能有效控制垂直度并避免混凝土错台。
High-rise building bay window aluminum alloy formwork mounting and reinforcing method
The invention discloses a mounting and reinforcing method for a bay window aluminum alloy formwork of a high-rise building, and belongs to the field of house construction engineering. The floating plate specifically comprises a floating plate cover plate, a floating plate bottom plate, a supporting rod, an early-dismantling head, an anti-floating back ridge, a long opposite-pull rod, a K plate, an embedded bolt, a short wall plate, a corner plate, a short opposite-pull rod, an angle plate, a gasket and an edge sealing plate. According to the method for installing and reinforcing the bay window aluminum alloy formwork of the high-rise building, the bolt holes are reserved in the lower-layer beam in advance, when the upper-layer formwork is erected, the K plate is fixed through the embedded bolts, the fixation of the K plate can effectively support a low wall plate on the upper portion, the formwork on the upper portion cannot fall off or displace, the effect of supporting the aluminum formwork on the upper portion is achieved, and the construction period is shortened. And the perpendicularity can be effectively controlled, and concrete slab staggering is avoided.
本发明公开了一种高层建筑飘窗铝合金模板安装加固方法,属于房屋建设工程领域。具体包括以下:飘板盖板、飘板底板、支撑杆、早拆头、抗上浮背楞、长对拉杆、K板、预埋螺栓、矮墙板、转角板、短对拉杆、角板、垫片、封边板。本发明的一种高层建筑飘窗铝合金模板安装加固方法,提前在下层梁内预留的螺栓孔,在支设上层模板时,采用预埋螺栓将K板固定,K板的固定能有效支撑上部的矮墙板,使上部的模板不会发生掉落及位移,达到支撑上部铝模板的作用,并能有效控制垂直度并避免混凝土错台。
High-rise building bay window aluminum alloy formwork mounting and reinforcing method
一种高层建筑飘窗铝合金模板安装加固方法
LIU QUBO (author) / ZHANG HAILIN (author) / HE ZHENYANG (author)
2022-08-09
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Reinforcing structure for bay window aluminum alloy formwork
European Patent Office | 2024
|Aluminum alloy formwork wall end reinforcing assembly and mounting method
European Patent Office | 2024
|Aluminum alloy formwork construction method for high-rise building
European Patent Office | 2022
|