Soil reinforcement method for pipeline traction construction
A soil reinforcement method for traction pipeline construction is characterized by comprising the following steps of a, arranging a grouting pipeline on a traction pipeline, b, arranging the grouting pipeline on the traction pipeline for synchronous traction, c, grouting the grouting pipeline, and d, reinforcing original soil texture with cement grout. The soil reinforcement method for the traction pipeline construction has the advantages that reinforcement measures are convenient to manufacture, operation is easy, synchronous treatment is conducted in the construction process, the influence is small, time is short, the probability of potential safety hazards is reduced, the cost is low, the effect is good, and the rework cost is greatly reduced.
一种牵拉管道施工的土质加固方法,其特征在于包括以下步骤:a、牵拉管道配置注浆管道,b、牵拉管道配置注浆管道同步牵拉,c、注浆管道注浆,d、水泥浆液加固原土土质。本发明的牵拉管道施工的土质加固方法具有加固措施制作方便、操作简单,在施工过程中同步处理,影响少、时间短,降低发生安全隐患的概率,费用低,效果好和大幅降低返工成本的优点。
Soil reinforcement method for pipeline traction construction
A soil reinforcement method for traction pipeline construction is characterized by comprising the following steps of a, arranging a grouting pipeline on a traction pipeline, b, arranging the grouting pipeline on the traction pipeline for synchronous traction, c, grouting the grouting pipeline, and d, reinforcing original soil texture with cement grout. The soil reinforcement method for the traction pipeline construction has the advantages that reinforcement measures are convenient to manufacture, operation is easy, synchronous treatment is conducted in the construction process, the influence is small, time is short, the probability of potential safety hazards is reduced, the cost is low, the effect is good, and the rework cost is greatly reduced.
一种牵拉管道施工的土质加固方法,其特征在于包括以下步骤:a、牵拉管道配置注浆管道,b、牵拉管道配置注浆管道同步牵拉,c、注浆管道注浆,d、水泥浆液加固原土土质。本发明的牵拉管道施工的土质加固方法具有加固措施制作方便、操作简单,在施工过程中同步处理,影响少、时间短,降低发生安全隐患的概率,费用低,效果好和大幅降低返工成本的优点。
Soil reinforcement method for pipeline traction construction
一种牵拉管道施工的土质加固方法
WANG ZHIHAI (author) / HU MINGJIE (author) / YAN HONGCHUN (author) / LI GUOFU (author) / SHANG QIJIA (author)
2022-09-16
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pipeline construction directional traction tapping machine and construction method thereof
European Patent Office | 2021
|Construction method for existing pipeline reinforcement protection
European Patent Office | 2020
|Slope reinforcement construction method using vegetation soil and slope reinforcement construction
European Patent Office | 2021
|