Fabricated building process full-interpenetration construction method
The invention discloses an assembly type building process full-interpenetration construction method, and relates to the technical field of building construction, and the method comprises the steps of composite floor slab installation, prefabricated stair slab installation and partition wall installation; the composite floor slab installation comprises the following steps of line position control, specifically, a horizontal control line of a composite slab is popped up before installation, the installation direction is marked on the composite slab, a cross line is made along the center of a pipe and the center of a hole, and marks are made on the edge of a prefabricated slab and the upper end of an installation wall beam; an elevation control line is arranged on the concrete wall, and the elevation of the bottom of the prefabricated slab floor is given; mounting a laminated slab bracket; elevation correction of mounting positions; concrete pouring of beams and shear walls; concrete pouring of the beams and the shear walls and concrete of the first floor slab, and connection points of the prefabricated slabs and the walls and the beams are located at the tops of the side formworks; and component installation. Compared with the prior art, the fabricated building interpenetrating construction method has the advantages that energy consumption is reduced, the construction site is neater and more orderly, and the green and environment-friendly construction concept is better embodied.
本申请公开一种装配式建筑工序全穿插施工方法,涉及建筑施工技术领域,包括叠合楼板安装、预制楼梯板安装、隔板墙安装;叠合楼板安装包括以下步骤:线位控制:安装前先弹好叠合板水平控制线,在叠合板上标明安装方向,沿着管、洞中心做十字交叉线,在预制板的边缘和安装墙梁的上端都做好标识;在混凝土墙上打好标高控制线,给定预制板楼板底部的标高;叠合板支架安装;安装位置标高校正:梁、剪力墙混凝土浇筑:梁和剪力墙混凝土和楼板一砼浇筑,预制板与墙和梁的衔接点在侧模顶部;构件安装。本申请使用的装配式建筑穿插施工方法与现有技术相比节约能耗,施工现场更加整洁有序,更加体现绿色环保的施工理念。
Fabricated building process full-interpenetration construction method
The invention discloses an assembly type building process full-interpenetration construction method, and relates to the technical field of building construction, and the method comprises the steps of composite floor slab installation, prefabricated stair slab installation and partition wall installation; the composite floor slab installation comprises the following steps of line position control, specifically, a horizontal control line of a composite slab is popped up before installation, the installation direction is marked on the composite slab, a cross line is made along the center of a pipe and the center of a hole, and marks are made on the edge of a prefabricated slab and the upper end of an installation wall beam; an elevation control line is arranged on the concrete wall, and the elevation of the bottom of the prefabricated slab floor is given; mounting a laminated slab bracket; elevation correction of mounting positions; concrete pouring of beams and shear walls; concrete pouring of the beams and the shear walls and concrete of the first floor slab, and connection points of the prefabricated slabs and the walls and the beams are located at the tops of the side formworks; and component installation. Compared with the prior art, the fabricated building interpenetrating construction method has the advantages that energy consumption is reduced, the construction site is neater and more orderly, and the green and environment-friendly construction concept is better embodied.
本申请公开一种装配式建筑工序全穿插施工方法,涉及建筑施工技术领域,包括叠合楼板安装、预制楼梯板安装、隔板墙安装;叠合楼板安装包括以下步骤:线位控制:安装前先弹好叠合板水平控制线,在叠合板上标明安装方向,沿着管、洞中心做十字交叉线,在预制板的边缘和安装墙梁的上端都做好标识;在混凝土墙上打好标高控制线,给定预制板楼板底部的标高;叠合板支架安装;安装位置标高校正:梁、剪力墙混凝土浇筑:梁和剪力墙混凝土和楼板一砼浇筑,预制板与墙和梁的衔接点在侧模顶部;构件安装。本申请使用的装配式建筑穿插施工方法与现有技术相比节约能耗,施工现场更加整洁有序,更加体现绿色环保的施工理念。
Fabricated building process full-interpenetration construction method
装配式建筑工序全穿插施工方法
HE SHIPIN (author) / LENG WEI (author) / HAN XUECHI (author) / HUANG DAOLOU (author) / ZHAO BIAO (author) / JIA QI (author) / ZHANG JIAWEI (author)
2022-09-30
Patent
Electronic Resource
Chinese
Full-interpenetration construction method based on northern constructional engineering
European Patent Office | 2021
|Construction method of full-fabricated concrete building system
European Patent Office | 2021
|INTERPENETRATION APPARATUS FOR MARINE MONOPILE AND THE INTERPENETRATION METHOD USING THIS
European Patent Office | 2022
|