The invention discloses a construction method of a linear accelerator machine room. The construction method comprises the steps that S1, steel bar engineering is conducted, specifically, shear wall steel bars are bound, and in-wall temperature measuring points are arranged; s2, formwork engineering: shear wall formwork construction, inner wall thermal insulation layer construction, line snapping, peripheral stand column and cross bridging construction, plate formwork support construction, plate steel bar construction, in-plate temperature measurement point arrangement, plate side formwork construction, outer wall thermal insulation layer construction and hidden inspection; and S3, concrete engineering: concrete pouring and plate surface thermal insulation construction. A threaded screw is adopted, the tolerance between the inside and the outside of the screw is 50 mm, a T-shaped wall and a straight wall in a machine room are both reinforced through opposite-pull screws, a door opening is in a full-thread and half-thread three-section type, reverse threads are formed in the surface of the used screw, and the thread opening of the reverse threads makes contact with concrete in a staggered mode, so that the screw is more tightly engaged with the concrete, and the service life of the screw is prolonged. Ray escape when the screw is in parallel contact with the concrete is avoided, so that the radiation protection performance of the linear accelerator machine room is enhanced.
本发明公开了一种直线加速器机房的施工方法,包括S1、钢筋工程:剪力墙钢筋绑扎→布置墙内测温点;S2、模板工程:剪力墙模板施工→内墙保温层施工→弹线→四周立柱及剪刀撑施工→板模板支撑施工→板钢筋施工→布置板内测温点→板侧模施工→外墙保温层施工→隐检;S3、混凝土工程:混凝土浇筑→板表面保温施工。本发明中采用有螺纹螺杆,螺杆内外有50mm公差,机房内的丁字墙、直墙均采用对拉螺杆加强,门洞采用全螺纹和半螺纹三段式形式,在使用的螺杆表面开设有倒牙,其牙口与混凝土交错接触,使螺杆与混凝土咬合更紧密,避免了螺杆与混凝土平行接触时的射线逃逸,使得本直线加速器机房防辐射性能增强。
Construction method of linear accelerator machine room
The invention discloses a construction method of a linear accelerator machine room. The construction method comprises the steps that S1, steel bar engineering is conducted, specifically, shear wall steel bars are bound, and in-wall temperature measuring points are arranged; s2, formwork engineering: shear wall formwork construction, inner wall thermal insulation layer construction, line snapping, peripheral stand column and cross bridging construction, plate formwork support construction, plate steel bar construction, in-plate temperature measurement point arrangement, plate side formwork construction, outer wall thermal insulation layer construction and hidden inspection; and S3, concrete engineering: concrete pouring and plate surface thermal insulation construction. A threaded screw is adopted, the tolerance between the inside and the outside of the screw is 50 mm, a T-shaped wall and a straight wall in a machine room are both reinforced through opposite-pull screws, a door opening is in a full-thread and half-thread three-section type, reverse threads are formed in the surface of the used screw, and the thread opening of the reverse threads makes contact with concrete in a staggered mode, so that the screw is more tightly engaged with the concrete, and the service life of the screw is prolonged. Ray escape when the screw is in parallel contact with the concrete is avoided, so that the radiation protection performance of the linear accelerator machine room is enhanced.
本发明公开了一种直线加速器机房的施工方法,包括S1、钢筋工程:剪力墙钢筋绑扎→布置墙内测温点;S2、模板工程:剪力墙模板施工→内墙保温层施工→弹线→四周立柱及剪刀撑施工→板模板支撑施工→板钢筋施工→布置板内测温点→板侧模施工→外墙保温层施工→隐检;S3、混凝土工程:混凝土浇筑→板表面保温施工。本发明中采用有螺纹螺杆,螺杆内外有50mm公差,机房内的丁字墙、直墙均采用对拉螺杆加强,门洞采用全螺纹和半螺纹三段式形式,在使用的螺杆表面开设有倒牙,其牙口与混凝土交错接触,使螺杆与混凝土咬合更紧密,避免了螺杆与混凝土平行接触时的射线逃逸,使得本直线加速器机房防辐射性能增强。
Construction method of linear accelerator machine room
一种直线加速器机房的施工方法
LIU LIHANG (author) / GUO XINFENG (author) / YE YILEI (author) / LIU WENMEI (author) / JIN KUNYANG (author)
2022-11-22
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Wallboard construction method of linear accelerator machine room
European Patent Office | 2022
|Ray penetration prevention construction method for linear accelerator machine room
European Patent Office | 2024
|Concrete construction method for super-long large-size linear accelerator machine room
European Patent Office | 2024
|Linear accelerator radiotherapy room structure and construction method thereof
European Patent Office | 2020
|European Patent Office | 2021
|