Steel truss girder pushing temporary pier structure in strong tidal bore area and construction method of steel truss girder pushing temporary pier structure
The invention relates to a strong tidal bore area steel truss girder pushing temporary pier structure and a construction method thereof, the strong tidal bore area steel truss girder pushing temporary pier structure comprises pushing distribution beams, cast-in-situ bored pile foundations, vertical columns and horizontal supports, and the cast-in-situ bored pile foundations are formed at the lower ends of the vertical columns in a pouring mode so as to guarantee the installation stability of the vertical columns; the two vertical stand columns are arranged in parallel, the horizontal supports are fixedly welded between the adjacent vertical stand columns to form a single pier column face, the two pier column faces are arranged in parallel, and the adjacent pier column faces are connected through the transverse connecting structures to form a unit temporary pier column. The temporary pier column structure is provided with a vertical structure system with certain vertical bearing capacity, and a pushing distribution beam is fixedly connected to a unit temporary pier column.
一种强涌潮区域钢桁梁顶推临时墩结构及其施工方法,包括顶推分配梁、钻孔灌注桩基础、竖向立柱和水平支撑,在每个竖向立柱的下端浇筑成形有钻孔灌注桩基础,以保证竖向立柱的安装稳定性;两根竖向立柱平行设置,在相邻的竖向立柱之间固定焊接水平支撑从而形成单个墩柱面,两个墩柱面平行布设,相邻的墩柱面之间通过横向连接结构相互连接,从而形成一个单位临时墩柱,该临时墩柱结构具有一定竖向承载能力的竖向结构体系,顶推分配梁固定连接在单位临时墩柱上。
Steel truss girder pushing temporary pier structure in strong tidal bore area and construction method of steel truss girder pushing temporary pier structure
The invention relates to a strong tidal bore area steel truss girder pushing temporary pier structure and a construction method thereof, the strong tidal bore area steel truss girder pushing temporary pier structure comprises pushing distribution beams, cast-in-situ bored pile foundations, vertical columns and horizontal supports, and the cast-in-situ bored pile foundations are formed at the lower ends of the vertical columns in a pouring mode so as to guarantee the installation stability of the vertical columns; the two vertical stand columns are arranged in parallel, the horizontal supports are fixedly welded between the adjacent vertical stand columns to form a single pier column face, the two pier column faces are arranged in parallel, and the adjacent pier column faces are connected through the transverse connecting structures to form a unit temporary pier column. The temporary pier column structure is provided with a vertical structure system with certain vertical bearing capacity, and a pushing distribution beam is fixedly connected to a unit temporary pier column.
一种强涌潮区域钢桁梁顶推临时墩结构及其施工方法,包括顶推分配梁、钻孔灌注桩基础、竖向立柱和水平支撑,在每个竖向立柱的下端浇筑成形有钻孔灌注桩基础,以保证竖向立柱的安装稳定性;两根竖向立柱平行设置,在相邻的竖向立柱之间固定焊接水平支撑从而形成单个墩柱面,两个墩柱面平行布设,相邻的墩柱面之间通过横向连接结构相互连接,从而形成一个单位临时墩柱,该临时墩柱结构具有一定竖向承载能力的竖向结构体系,顶推分配梁固定连接在单位临时墩柱上。
Steel truss girder pushing temporary pier structure in strong tidal bore area and construction method of steel truss girder pushing temporary pier structure
一种强涌潮区域钢桁梁顶推临时墩结构及其施工方法
ZHU MENGYAN (author) / LI SHENGHUI (author) / CHEN HAO (author) / LIN GUOBIN (author) / ZHAO KAI (author) / XIE ZHENJIE (author) / JIANG SHENGHANG (author) / LIU YANG (author) / ZHANG GAOJIE (author)
2022-12-02
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Pier placing device for pushing steel truss girder bridge and use method of pier placing device
European Patent Office | 2023
|Steel truss girder pushing device for bridge construction
European Patent Office | 2024
|Pushing device for steel truss and pier loading method for steel truss
European Patent Office | 2024
|