Cover beam construction system and method
The bent cap construction system comprises a formwork system, a construction platform system and a supporting system, the formwork system is arranged on a construction platform, the supporting system is arranged above a bridge pier, and an embedded part is arranged in the bridge pier and used for installing the supporting system; a lifting mechanism used for lifting the construction platform system is arranged on the supporting system, so that the construction platform system can move in the length direction of the pier, and the supporting system can be used for stably supporting the construction platform system after the construction platform system is lifted in place; according to the bent cap construction system in the scheme, the construction platform system can be assembled on the ground along the size of the bridge pier, then the construction platform system is lifted through the lifting mechanism of the supporting system, when the construction platform system is lifted to a preset position, the construction platform system and the supporting system are fixed, then the formwork system is assembled, and the construction platform system and the formwork system are assembled. By means of the scheme, the time for assembling the construction platform system at high altitude can be shortened.
本发明公开了一种盖梁施工体系及方法,包括模板系统、施工平台系统和支撑系统,模板系统设置于施工平台之上,支撑系统设于桥墩上方,桥墩内设有预埋件,预埋件用于安装支撑系统;支撑系统上设置有用于提升施工平台系统的提升机构,使施工平台系统能够沿桥墩的长度方向进行移动,且支撑系统能够用于在施工平台系统提升到位后对其稳固支撑;本方案中的盖梁施工体系,可以将施工平台系统在地面上沿桥墩的大小进行组装好,然后再通过支撑系统的提升机构将施工平台系统进行提升,当提升到预定位置时,将施工平台系统与支撑系统进行固定,再将模板系统进行装配,浇筑混凝土进行盖梁的制备,通过本方案,可以减小在高空装配施工平台系统的时间。
Cover beam construction system and method
The bent cap construction system comprises a formwork system, a construction platform system and a supporting system, the formwork system is arranged on a construction platform, the supporting system is arranged above a bridge pier, and an embedded part is arranged in the bridge pier and used for installing the supporting system; a lifting mechanism used for lifting the construction platform system is arranged on the supporting system, so that the construction platform system can move in the length direction of the pier, and the supporting system can be used for stably supporting the construction platform system after the construction platform system is lifted in place; according to the bent cap construction system in the scheme, the construction platform system can be assembled on the ground along the size of the bridge pier, then the construction platform system is lifted through the lifting mechanism of the supporting system, when the construction platform system is lifted to a preset position, the construction platform system and the supporting system are fixed, then the formwork system is assembled, and the construction platform system and the formwork system are assembled. By means of the scheme, the time for assembling the construction platform system at high altitude can be shortened.
本发明公开了一种盖梁施工体系及方法,包括模板系统、施工平台系统和支撑系统,模板系统设置于施工平台之上,支撑系统设于桥墩上方,桥墩内设有预埋件,预埋件用于安装支撑系统;支撑系统上设置有用于提升施工平台系统的提升机构,使施工平台系统能够沿桥墩的长度方向进行移动,且支撑系统能够用于在施工平台系统提升到位后对其稳固支撑;本方案中的盖梁施工体系,可以将施工平台系统在地面上沿桥墩的大小进行组装好,然后再通过支撑系统的提升机构将施工平台系统进行提升,当提升到预定位置时,将施工平台系统与支撑系统进行固定,再将模板系统进行装配,浇筑混凝土进行盖梁的制备,通过本方案,可以减小在高空装配施工平台系统的时间。
Cover beam construction system and method
一种盖梁施工体系及方法
LIU YANLONG (author) / WANG YICHUN (author) / JIANG BIN (author) / TIAN YE (author) / KONG QINGHUI (author) / ZHAO XIN (author) / ZHANG HONGJUN (author) / QU YANQIANG (author) / LI HAIRUO (author) / LI LEI (author)
2022-12-13
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Movable cover beam support structure and cover beam construction system