A platform for research: civil engineering, architecture and urbanism
Concrete batter post construction method
The invention discloses a concrete batter post construction method, which belongs to the technical field of building engineering, and comprises the following steps: step 1, simulating through a BIM (Building Information Modeling) technology, exposing batter post construction, demonstrating key procedures, arranging a specially-assigned person to turn a sample on a batter post, drawing a sample turning drawing, and utilizing a computer to assist in turning the sample; 2, a construction scheme is compiled, technical disclosure and safety technical disclosure are carried out, and then laying out and positioning are carried out; step 3, drawing a projection ink line which is straight with the inclined column, constructing a supporting template, and fixing the column template by using a column hoop and a column penetrating bolt after checking the perpendicularity and the gradient; and 4, concrete is poured and maintained for 7 days with the mold, then the face mold and the side mold plates are removed, then the supporting frame is removed, and finally detection is completed in sequence. The invention provides a complete set of mature construction process, and reference can be provided for implementation of key technologies in similar engineering construction, so that the construction period is shortened, the cost is saved, and certain economic benefits are created.
本发明公开了一种混凝土斜柱施工方法,属于建筑工程技术领域,包括以下步骤:步骤一、通过BIM技术模拟,对斜柱施工进行交底,对关键工序进行演示,斜柱设专人翻样,绘制翻样图,并利用计算机辅助翻样;步骤二、编制施工方案,进行技术交底及安全技术交底,然后进行测设和定位;步骤三、画与斜柱平直的投影墨线,构建支撑模板,并检查垂直度、倾斜度后用柱箍和穿柱螺栓固定柱模;步骤四、浇筑混凝土,并带模养护7d,然后先将面模和侧模板拆除,再拆除支撑架,最后依次完成检测。本发明提供了成熟的成套施工工艺,可为类似工程施工中关键技术的实现提供借鉴,以缩短工期和节约成本,创造一定的经济效益。
Concrete batter post construction method
The invention discloses a concrete batter post construction method, which belongs to the technical field of building engineering, and comprises the following steps: step 1, simulating through a BIM (Building Information Modeling) technology, exposing batter post construction, demonstrating key procedures, arranging a specially-assigned person to turn a sample on a batter post, drawing a sample turning drawing, and utilizing a computer to assist in turning the sample; 2, a construction scheme is compiled, technical disclosure and safety technical disclosure are carried out, and then laying out and positioning are carried out; step 3, drawing a projection ink line which is straight with the inclined column, constructing a supporting template, and fixing the column template by using a column hoop and a column penetrating bolt after checking the perpendicularity and the gradient; and 4, concrete is poured and maintained for 7 days with the mold, then the face mold and the side mold plates are removed, then the supporting frame is removed, and finally detection is completed in sequence. The invention provides a complete set of mature construction process, and reference can be provided for implementation of key technologies in similar engineering construction, so that the construction period is shortened, the cost is saved, and certain economic benefits are created.
本发明公开了一种混凝土斜柱施工方法,属于建筑工程技术领域,包括以下步骤:步骤一、通过BIM技术模拟,对斜柱施工进行交底,对关键工序进行演示,斜柱设专人翻样,绘制翻样图,并利用计算机辅助翻样;步骤二、编制施工方案,进行技术交底及安全技术交底,然后进行测设和定位;步骤三、画与斜柱平直的投影墨线,构建支撑模板,并检查垂直度、倾斜度后用柱箍和穿柱螺栓固定柱模;步骤四、浇筑混凝土,并带模养护7d,然后先将面模和侧模板拆除,再拆除支撑架,最后依次完成检测。本发明提供了成熟的成套施工工艺,可为类似工程施工中关键技术的实现提供借鉴,以缩短工期和节约成本,创造一定的经济效益。
Concrete batter post construction method
一种混凝土斜柱施工方法
XIA GUANGLIANG (author) / XU RUIQING (author)
2022-12-27
Patent
Electronic Resource
Chinese
IPC:
G06Q
Datenverarbeitungssysteme oder -verfahren, besonders angepasst an verwaltungstechnische, geschäftliche, finanzielle oder betriebswirtschaftliche Zwecke, sowie an geschäftsbezogene Überwachungs- oder Voraussagezwecke
,
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES
/
E04C
STRUCTURAL ELEMENTS
,
Bauelemente
/
E04G
SCAFFOLDING
,
Baugerüste
Construction method of large-section concrete batter post
European Patent Office | 2024
|Protective dismantling construction device for concrete batter post
European Patent Office | 2022
|Support-free construction method for V-shaped reinforced concrete batter post
European Patent Office | 2024
|Construction method of large-diameter circular steel reinforced concrete batter post
European Patent Office | 2023
|Construction method for steel reinforced concrete batter post of underground structure
European Patent Office | 2022
|