Construction method for safely replacing coal mine explosion door
The invention discloses a construction method for safely replacing a coal mine explosion door. The construction method comprises the following steps that S1, a novel explosion door foundation is installed; s2, a pre-embedded top plate and a pre-embedded bottom plate are installed; s3, wedge-shaped door columns are installed; s4, a buffer device is installed; s5, door frame assembly is installed; s6, installing an air reversing locking device; s7, installing and debugging the electric control system to a normal operation state; and S8, testing for many times and detecting whether the novel explosion door operates normally, and if the novel explosion door can operate normally, dismantling the traditional explosion door. The anti-explosion door has the effect that the anti-explosion door can be replaced conveniently.
本申请公开了一种安全更换煤矿防爆门的施工方法,其包括如下步骤:S1、安装新式防爆门基础;S2、安装预埋顶板和预埋底板;S3、安装楔形门柱;S4、安装缓冲装置;S5、安装门框装配;S6、安装反风锁紧装置;S7、安装并调试电控系统至正常运行状态;S8、多次试验并检测新式防爆门是否正常运行,若能正常运行,将传统防爆门拆除。本申请具有便于对防爆门进行更换的效果。
Construction method for safely replacing coal mine explosion door
The invention discloses a construction method for safely replacing a coal mine explosion door. The construction method comprises the following steps that S1, a novel explosion door foundation is installed; s2, a pre-embedded top plate and a pre-embedded bottom plate are installed; s3, wedge-shaped door columns are installed; s4, a buffer device is installed; s5, door frame assembly is installed; s6, installing an air reversing locking device; s7, installing and debugging the electric control system to a normal operation state; and S8, testing for many times and detecting whether the novel explosion door operates normally, and if the novel explosion door can operate normally, dismantling the traditional explosion door. The anti-explosion door has the effect that the anti-explosion door can be replaced conveniently.
本申请公开了一种安全更换煤矿防爆门的施工方法,其包括如下步骤:S1、安装新式防爆门基础;S2、安装预埋顶板和预埋底板;S3、安装楔形门柱;S4、安装缓冲装置;S5、安装门框装配;S6、安装反风锁紧装置;S7、安装并调试电控系统至正常运行状态;S8、多次试验并检测新式防爆门是否正常运行,若能正常运行,将传统防爆门拆除。本申请具有便于对防爆门进行更换的效果。
Construction method for safely replacing coal mine explosion door
一种安全更换煤矿防爆门的施工方法
YANG SHOUGANG (author) / ZHANG JUNWEN (author) / HU YUNYUN (author) / LI YONGTAO (author) / XU YONG (author) / MENG YANG (author)
2023-02-03
Patent
Electronic Resource
Chinese
IPC:
E21F
Sicherheitsvorrichtungen, Förderung, Auffüllen oder Bergversatz, Rettungswesen, Bewetterung oder Entwässerung in oder von Gruben oder Tunnels
,
SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINAGE IN OR OF MINES OR TUNNELS
/
E06B
Feste oder bewegliche Abschlüsse für Öffnungen in Bauwerken, Fahrzeugen, Zäunen oder ähnlichen Einfriedungen allgemein, z.B. Türen, Fenster, Läden, Tore
,
FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES, OR LIKE ENCLOSURES, IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
European Patent Office | 2021
|Stably-connected explosion venting door special for mine electromechanics
European Patent Office | 2024
|