Assembly type concrete prefabricated part mounting method
The invention belongs to the technical field of fabricated buildings, and particularly relates to a fabricated concrete prefabricated part mounting method which comprises the steps of prefabricated part hoisting in place, primary grouting horizontal adjustment, secondary pressurizing vertical adjustment, pressure keeping condensation and watering maintenance. The horizontal adjusting part in the prefabricated part works in a grouting mode, then the position deviation of the newly-installed prefabricated part in the horizontal direction is adjusted in the grouting connection process, and due to the fact that the adjusting part in the horizontal direction is arranged on the prefabricated part in the scheme, in the hoisting process, the position deviation of the newly-installed prefabricated part in the horizontal direction is adjusted. According to the technical scheme, the corners of the prefabricated part do not need to be accurately aligned, so that the position does not need to be accurately adjusted in the hoisting process, the hoisting workload is reduced, meanwhile, participation of position adjusting personnel in the hoisting process is reduced, the construction efficiency is higher, and the safety in the construction process is improved.
本发明属于装配式建筑技术领域,具体的说是一种装配式混凝土预制件安装方法,包括预制件吊装到位、一次注浆水平调整、二次加压竖直调整、保持压力凝结和洒水养生;本发明中通过注浆的形式使得预制件中的水平调节部件工作,进而在注浆连接的过程中使得新安装的预制件在水平方向的位置偏差得到调整,由于该方案中预制件上设置有水平方向的调整部件,进而使得在吊装的过程中,不需要很精准的使得预制件的边角处对齐,进而使得吊装的过程中不需要精准的调整位置,进而减少了吊装的工作量,同时也减少了吊装过程中位置调整人员的参与,进而使得施工的效率更高和施工过程中的安全性的增加。
Assembly type concrete prefabricated part mounting method
The invention belongs to the technical field of fabricated buildings, and particularly relates to a fabricated concrete prefabricated part mounting method which comprises the steps of prefabricated part hoisting in place, primary grouting horizontal adjustment, secondary pressurizing vertical adjustment, pressure keeping condensation and watering maintenance. The horizontal adjusting part in the prefabricated part works in a grouting mode, then the position deviation of the newly-installed prefabricated part in the horizontal direction is adjusted in the grouting connection process, and due to the fact that the adjusting part in the horizontal direction is arranged on the prefabricated part in the scheme, in the hoisting process, the position deviation of the newly-installed prefabricated part in the horizontal direction is adjusted. According to the technical scheme, the corners of the prefabricated part do not need to be accurately aligned, so that the position does not need to be accurately adjusted in the hoisting process, the hoisting workload is reduced, meanwhile, participation of position adjusting personnel in the hoisting process is reduced, the construction efficiency is higher, and the safety in the construction process is improved.
本发明属于装配式建筑技术领域,具体的说是一种装配式混凝土预制件安装方法,包括预制件吊装到位、一次注浆水平调整、二次加压竖直调整、保持压力凝结和洒水养生;本发明中通过注浆的形式使得预制件中的水平调节部件工作,进而在注浆连接的过程中使得新安装的预制件在水平方向的位置偏差得到调整,由于该方案中预制件上设置有水平方向的调整部件,进而使得在吊装的过程中,不需要很精准的使得预制件的边角处对齐,进而使得吊装的过程中不需要精准的调整位置,进而减少了吊装的工作量,同时也减少了吊装过程中位置调整人员的参与,进而使得施工的效率更高和施工过程中的安全性的增加。
Assembly type concrete prefabricated part mounting method
一种装配式混凝土预制件安装方法
YANG BING (author) / LI LIN (author) / LI HAIYANG (author) / WANG JIADONG (author)
2023-03-21
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Prefabricated assembly type steel-concrete part mounting device
European Patent Office | 2023
|Assembly type prefabricated reinforced concrete prefabricated part
European Patent Office | 2021
|Assembly type building prefabricated part mounting equipment
European Patent Office | 2023
|Assembly type building prefabricated part mounting equipment
European Patent Office | 2023
|