Construction technology of bridge pier bearing platform
The invention relates to a construction technology of a bridge pier bearing platform, and belongs to the technical field of bridge construction, and the construction technology comprises the following steps: S1, surveying personnel carries out surveying and setting out, and excavates a foundation pit; s2, cushion concrete is poured at the bottom of the foundation pit; s3, steel bar binding is carried out according to the surveying and setting-out position; s4, mounting a bearing template; s5, concrete pouring is conducted on the bearing platform, vibrating equipment is started in the pouring process, the vibrating equipment comprises a driving device and a vibrating rod, the vibrating rod is installed on the driving device, the vibrating rod penetrates through the formwork, the vibrating rod is in sliding connection with the formwork, the vibrating rod is used for vibrating concrete at the bottom of the bearing platform, and the driving device is used for providing power for the vibrating rod; and S6, after concrete pouring is completed, the concrete meets the strength requirement, and the vibrating equipment and the formwork are dismantled. The method has the effect of improving the quality of the bearing platform.
本申请涉及一种桥梁墩承台的施工工艺,属于桥梁施工的技术领域,其包括以下步骤:S1、测量人员进行测量放线,对基坑进行开挖;S2、对基坑底部进行垫层混凝土的浇筑;S3、根据测量放线的位置,进行钢筋绑扎;S4、安装承载模板;S5、对承台进行混凝土浇筑,在浇筑的过程中启动振捣设备,振捣设备包括驱动装置和振捣棒,振捣棒安装在驱动装置上,振捣棒穿过模板,振捣棒和模板滑动连接,振捣棒用于对承台底部的混凝土进行振捣,驱动装置用于为振捣棒提供动力;S6、在对混凝土浇筑完成后,混凝土达到强度要求,对振捣设备以及模板进行拆除。本申请具有提高承台质量的效果。
Construction technology of bridge pier bearing platform
The invention relates to a construction technology of a bridge pier bearing platform, and belongs to the technical field of bridge construction, and the construction technology comprises the following steps: S1, surveying personnel carries out surveying and setting out, and excavates a foundation pit; s2, cushion concrete is poured at the bottom of the foundation pit; s3, steel bar binding is carried out according to the surveying and setting-out position; s4, mounting a bearing template; s5, concrete pouring is conducted on the bearing platform, vibrating equipment is started in the pouring process, the vibrating equipment comprises a driving device and a vibrating rod, the vibrating rod is installed on the driving device, the vibrating rod penetrates through the formwork, the vibrating rod is in sliding connection with the formwork, the vibrating rod is used for vibrating concrete at the bottom of the bearing platform, and the driving device is used for providing power for the vibrating rod; and S6, after concrete pouring is completed, the concrete meets the strength requirement, and the vibrating equipment and the formwork are dismantled. The method has the effect of improving the quality of the bearing platform.
本申请涉及一种桥梁墩承台的施工工艺,属于桥梁施工的技术领域,其包括以下步骤:S1、测量人员进行测量放线,对基坑进行开挖;S2、对基坑底部进行垫层混凝土的浇筑;S3、根据测量放线的位置,进行钢筋绑扎;S4、安装承载模板;S5、对承台进行混凝土浇筑,在浇筑的过程中启动振捣设备,振捣设备包括驱动装置和振捣棒,振捣棒安装在驱动装置上,振捣棒穿过模板,振捣棒和模板滑动连接,振捣棒用于对承台底部的混凝土进行振捣,驱动装置用于为振捣棒提供动力;S6、在对混凝土浇筑完成后,混凝土达到强度要求,对振捣设备以及模板进行拆除。本申请具有提高承台质量的效果。
Construction technology of bridge pier bearing platform
一种桥梁墩承台的施工工艺
RA JIN (author) / MIAO LONGLONG (author) / XU XUEZHENG (author) / MAO YONGMING (author) / LI ZHOUJIE (author) / ZANG JIANXIN (author) / SUN MENGMENG (author) / LIU TIEJUN (author) / WANG JIYANG (author) / SU XIANSHU (author)
2023-05-05
Patent
Electronic Resource
Chinese
Construction method of overwater bridge main pier bearing platform
European Patent Office | 2024
|Bridge main pier bearing platform and tower base construction method
European Patent Office | 2023
|Construction scaffold for dismounting bridge bearing platform pier column template
European Patent Office | 2023
|