Fabricated high-pile wharf construction method
The invention relates to the technical field of high-pile wharf construction, in particular to an assembly type high-pile wharf construction method. The construction method comprises the following steps that S1, pile foundations are arranged at the construction position of the high-pile wharf in a driving mode, and meanwhile prefabricated core cap beam plates comprising beam plates, longitudinal beams, cross beams, pile caps and pile cores are prefabricated in a prefabrication factory; s2, the prefabricated core cap beam plate is carried to the construction position, the prefabricated core cap beam plate is hoisted based on hoisting equipment, and the pile core is inserted into the pile foundation; and S3, the pile cores and the pile foundations are fixed, joints between the adjacent prefabricated core cap beam plates are constructed, and construction of the high-pile wharf is completed. According to the construction method, the wharf surface layer channel is rapidly formed through integral prefabrication and integral hoisting of the prefabricated core cap beam plate, the labor safety is guaranteed, the engineering quality is improved, the wharf construction cost can be reduced, and good popularization significance is achieved.
本发明涉及高桩码头施工技术领域,具体地指一种装配式高桩码头施工方法。按照以下步骤进行:S1、于高桩码头施工位置打设桩基,同时在预制工厂内预制包含梁板、纵梁、横梁、桩帽和桩芯的预制芯帽梁板;S2、搬运预制芯帽梁板至施工位置,基于起重设备吊装预制芯帽梁板,将桩芯插入到桩基内;S3、对桩芯与桩基进行固定,施工相邻预制芯帽梁板之间的接缝,完成高桩码头的施工。本申请的施工方法通过预制芯帽梁板整体预制,整体吊装,快速形成码头面层通道,保证了用工安全,提高了工程质量,能降低码头施工成本,具有良好地推广意义。
Fabricated high-pile wharf construction method
The invention relates to the technical field of high-pile wharf construction, in particular to an assembly type high-pile wharf construction method. The construction method comprises the following steps that S1, pile foundations are arranged at the construction position of the high-pile wharf in a driving mode, and meanwhile prefabricated core cap beam plates comprising beam plates, longitudinal beams, cross beams, pile caps and pile cores are prefabricated in a prefabrication factory; s2, the prefabricated core cap beam plate is carried to the construction position, the prefabricated core cap beam plate is hoisted based on hoisting equipment, and the pile core is inserted into the pile foundation; and S3, the pile cores and the pile foundations are fixed, joints between the adjacent prefabricated core cap beam plates are constructed, and construction of the high-pile wharf is completed. According to the construction method, the wharf surface layer channel is rapidly formed through integral prefabrication and integral hoisting of the prefabricated core cap beam plate, the labor safety is guaranteed, the engineering quality is improved, the wharf construction cost can be reduced, and good popularization significance is achieved.
本发明涉及高桩码头施工技术领域,具体地指一种装配式高桩码头施工方法。按照以下步骤进行:S1、于高桩码头施工位置打设桩基,同时在预制工厂内预制包含梁板、纵梁、横梁、桩帽和桩芯的预制芯帽梁板;S2、搬运预制芯帽梁板至施工位置,基于起重设备吊装预制芯帽梁板,将桩芯插入到桩基内;S3、对桩芯与桩基进行固定,施工相邻预制芯帽梁板之间的接缝,完成高桩码头的施工。本申请的施工方法通过预制芯帽梁板整体预制,整体吊装,快速形成码头面层通道,保证了用工安全,提高了工程质量,能降低码头施工成本,具有良好地推广意义。
Fabricated high-pile wharf construction method
一种装配式高桩码头施工方法
FENG XIANDAO (author) / LUO ZHAO (author) / LIN HONGXING (author) / SUN WANJING (author) / SHEN LILONG (author) / LIU CONGCONG (author) / HE CONG (author) / YANG HANBIN (author) / QIU ZHENGZHONG (author) / CHEN DIYU (author)
2023-05-16
Patent
Electronic Resource
Chinese
European Patent Office | 2024
|Fabricated high-pile wharf structure and construction method thereof
European Patent Office | 2022
|Fabricated high-pile wharf joint and construction method thereof
European Patent Office | 2020
|Modular fabricated high-pile wharf structure and construction method thereof
European Patent Office | 2021
|