Slip form construction process for shear wall in silo
The invention relates to the technical field of building construction, in particular to a slip-form construction process for a shear wall in a silo, which comprises the following steps of: after steel bars of the silo wall and the shear wall in the silo are mounted and constructed to form silo wall steel bars and shear wall steel bars, forming a slip-form construction device for the silo wall and the shear wall in the silo by adopting an existing field slip-form tool; and then the slip-form construction process of the silo wall and the shear wall in the silo is synchronously carried out by utilizing the slip-form construction device. By means of the construction technology, the cost of wood formworks, steel pipes, fasteners, opposite-pull rod materials, installation cost and the like are saved, and potential safety hazards caused by steel pipe scaffold erection and follow-up construction are also reduced; and meanwhile, the silo wall and the shear wall in the silo are constructed synchronously, so that the construction time is greatly shortened, and better effects are achieved in the aspects of construction progress, safety, cost input and the like.
本发明涉及建筑施工技术领域,尤其涉及一种筒仓内剪力墙的滑模施工工艺,在进行筒仓仓壁和筒仓内剪力墙的钢筋安装施工以形成仓壁钢筋和剪力墙钢筋之后,采用已有的现场滑模工具形成筒仓仓壁和筒仓内剪力墙的滑模施工装置;然后利用该滑模施工装置同步进行筒仓仓壁和筒仓内剪力墙的滑模施工工艺。该施工工艺既节约了木模板、钢管、扣件、对拉杆材料及其安装等费用,也降低了钢管脚手架搭设及后续施工带来的安全隐患;同时,筒仓仓壁与筒仓内剪力墙同步施工,也大大缩短了施工时间,在施工进度、安全、成本投入等各方面都具有较佳的效果。
Slip form construction process for shear wall in silo
The invention relates to the technical field of building construction, in particular to a slip-form construction process for a shear wall in a silo, which comprises the following steps of: after steel bars of the silo wall and the shear wall in the silo are mounted and constructed to form silo wall steel bars and shear wall steel bars, forming a slip-form construction device for the silo wall and the shear wall in the silo by adopting an existing field slip-form tool; and then the slip-form construction process of the silo wall and the shear wall in the silo is synchronously carried out by utilizing the slip-form construction device. By means of the construction technology, the cost of wood formworks, steel pipes, fasteners, opposite-pull rod materials, installation cost and the like are saved, and potential safety hazards caused by steel pipe scaffold erection and follow-up construction are also reduced; and meanwhile, the silo wall and the shear wall in the silo are constructed synchronously, so that the construction time is greatly shortened, and better effects are achieved in the aspects of construction progress, safety, cost input and the like.
本发明涉及建筑施工技术领域,尤其涉及一种筒仓内剪力墙的滑模施工工艺,在进行筒仓仓壁和筒仓内剪力墙的钢筋安装施工以形成仓壁钢筋和剪力墙钢筋之后,采用已有的现场滑模工具形成筒仓仓壁和筒仓内剪力墙的滑模施工装置;然后利用该滑模施工装置同步进行筒仓仓壁和筒仓内剪力墙的滑模施工工艺。该施工工艺既节约了木模板、钢管、扣件、对拉杆材料及其安装等费用,也降低了钢管脚手架搭设及后续施工带来的安全隐患;同时,筒仓仓壁与筒仓内剪力墙同步施工,也大大缩短了施工时间,在施工进度、安全、成本投入等各方面都具有较佳的效果。
Slip form construction process for shear wall in silo
一种筒仓内剪力墙的滑模施工工艺
ZHAO GONG (author) / YANG KE (author) / ZHAO WENWEI (author)
2023-05-26
Patent
Electronic Resource
Chinese
Cylinder wall vertical deviation control method for silo slip form construction
European Patent Office | 2024
|Silo structure slip form construction maintenance device
European Patent Office | 2024
|