Construction and maintenance method for bridge body supporting part
The invention relates to the technical field of bridge engineering, and provides a construction and maintenance method for a bridge body supporting part, which comprises the following steps of: step 1, carrying out bearing platform construction, namely binding reinforcing steel bars, mounting a template of a bearing platform and pouring concrete of the bearing platform; 2, bearing platform concrete curing, concrete temperature control, bearing platform concrete temperature test point arrangement, temperature information monitoring and feedback and bearing platform water cooling are carried out; and 3, pier column construction, wherein pier column construction comprises the steps of support erection, pier column steel bar installation, pier column formwork installation, pier column concrete pouring and pier column concrete curing. On the basis, the effect of guaranteeing the quality of the supporting part of the bridge body is achieved by measuring and controlling the temperature of the concrete.
本申请涉及桥梁工程技术领域,提供了一种桥体支撑部的施工养护方法,其包括:步骤1:承台施工,承台施工包括:钢筋绑扎、承台的模板安装、承台混凝土浇筑;步骤2:承台混凝土养护,控制混凝土温度,承台混凝土温度测试点布置和温度信息监测反馈,承台通水冷却;步骤3:墩柱施工,墩柱施工包括,支架搭设、墩柱钢筋安装、墩柱模板安装、墩柱混凝土浇筑、墩柱混凝土养生。基于此,通过对混凝土的测温和控温,实现保证桥体的支撑部质量的效果。
Construction and maintenance method for bridge body supporting part
The invention relates to the technical field of bridge engineering, and provides a construction and maintenance method for a bridge body supporting part, which comprises the following steps of: step 1, carrying out bearing platform construction, namely binding reinforcing steel bars, mounting a template of a bearing platform and pouring concrete of the bearing platform; 2, bearing platform concrete curing, concrete temperature control, bearing platform concrete temperature test point arrangement, temperature information monitoring and feedback and bearing platform water cooling are carried out; and 3, pier column construction, wherein pier column construction comprises the steps of support erection, pier column steel bar installation, pier column formwork installation, pier column concrete pouring and pier column concrete curing. On the basis, the effect of guaranteeing the quality of the supporting part of the bridge body is achieved by measuring and controlling the temperature of the concrete.
本申请涉及桥梁工程技术领域,提供了一种桥体支撑部的施工养护方法,其包括:步骤1:承台施工,承台施工包括:钢筋绑扎、承台的模板安装、承台混凝土浇筑;步骤2:承台混凝土养护,控制混凝土温度,承台混凝土温度测试点布置和温度信息监测反馈,承台通水冷却;步骤3:墩柱施工,墩柱施工包括,支架搭设、墩柱钢筋安装、墩柱模板安装、墩柱混凝土浇筑、墩柱混凝土养生。基于此,通过对混凝土的测温和控温,实现保证桥体的支撑部质量的效果。
Construction and maintenance method for bridge body supporting part
一种桥体支撑部的施工养护方法
WAN CHENGFU (author) / LIU SIDE (author) / DENG CHAOYOU (author) / YAO ZHENGFEI (author) / WEN QIFU (author) / LONG GUOHUI (author) / ZHANG PANHUA (author) / LIU PENG (author) / XU JINHAI (author) / JIANG QINGHUA (author)