Chimney steel inner cylinder and hydraulic lifting upside-down construction method thereof
The invention relates to a chimney steel inner cylinder and a hydraulic lifting inverted construction method thereof, and relates to the field of building construction technology.The mounting method of the steel inner cylinder comprises the following steps that S1, a construction platform is mounted on the inner wall of an outer cylinder of a chimney, and a standard knot is lifted to the height slightly higher than that of the standard knot through a lifting device; s2, the next standard knot is placed under the lifted standard knot, and then the lifting device drives the lifted standard knot to descend, so that the mounting ring of the lower standard knot is sleeved with the mounting groove of the upper standard knot; s3, the rotating device is used for driving the upper standard knot to rotate, so that the connecting hole in the upper standard knot is coaxially aligned with the connecting hole in the lower standard knot, and then a fastener is arranged in the connecting hole in a penetrating mode to fix the connecting position of every two adjacent standard knots; and S4, the steps S1, S2 and S3 are repeated till all the other standard knots are installed. The method has the effect of effectively shortening the construction period of mounting the steel inner cylinder.
本申请涉及一种烟囱钢内筒及其液压提升倒装施工方法,涉及建筑施工技术的领域,钢内筒的安装方法包括如下步骤:S1、在烟囱的外筒内壁上安装施工平台,利用提升装置将一个标准节提升至略高于一个标准节的高度;S2、将下一标准节放置于已提升的标准节正下方,然后提升装置带动已提升的标准节下降,使得上方的标准节的安装槽套设于下方的标准节的安装环上;S3、利用转动装置带动上方的标准节转动,使得上方的标准节上的连接孔与下方标准节上的连接孔同轴对正,然后将紧固件穿设于连接孔内以将相邻两个标准节的连接处固定;S4、重复S1、S2和S3直至完成其余所有标准节的安装即可。本申请具有能够有效缩短安装钢内筒的施工周期的效果。
Chimney steel inner cylinder and hydraulic lifting upside-down construction method thereof
The invention relates to a chimney steel inner cylinder and a hydraulic lifting inverted construction method thereof, and relates to the field of building construction technology.The mounting method of the steel inner cylinder comprises the following steps that S1, a construction platform is mounted on the inner wall of an outer cylinder of a chimney, and a standard knot is lifted to the height slightly higher than that of the standard knot through a lifting device; s2, the next standard knot is placed under the lifted standard knot, and then the lifting device drives the lifted standard knot to descend, so that the mounting ring of the lower standard knot is sleeved with the mounting groove of the upper standard knot; s3, the rotating device is used for driving the upper standard knot to rotate, so that the connecting hole in the upper standard knot is coaxially aligned with the connecting hole in the lower standard knot, and then a fastener is arranged in the connecting hole in a penetrating mode to fix the connecting position of every two adjacent standard knots; and S4, the steps S1, S2 and S3 are repeated till all the other standard knots are installed. The method has the effect of effectively shortening the construction period of mounting the steel inner cylinder.
本申请涉及一种烟囱钢内筒及其液压提升倒装施工方法,涉及建筑施工技术的领域,钢内筒的安装方法包括如下步骤:S1、在烟囱的外筒内壁上安装施工平台,利用提升装置将一个标准节提升至略高于一个标准节的高度;S2、将下一标准节放置于已提升的标准节正下方,然后提升装置带动已提升的标准节下降,使得上方的标准节的安装槽套设于下方的标准节的安装环上;S3、利用转动装置带动上方的标准节转动,使得上方的标准节上的连接孔与下方标准节上的连接孔同轴对正,然后将紧固件穿设于连接孔内以将相邻两个标准节的连接处固定;S4、重复S1、S2和S3直至完成其余所有标准节的安装即可。本申请具有能够有效缩短安装钢内筒的施工周期的效果。
Chimney steel inner cylinder and hydraulic lifting upside-down construction method thereof
一种烟囱钢内筒及其液压提升倒装施工方法
2023-06-06
Patent
Electronic Resource
Chinese
Hydraulic lifting construction method for steel inner cylinder chimney
European Patent Office | 2022
|European Patent Office | 2021
|Hydraulic lifting construction device and method for inner steel barrel of chimney