A platform for research: civil engineering, architecture and urbanism
Culvert wall construction process
The invention discloses a culvert wall construction process which comprises the following steps: a foundation pouring step: pouring a concrete pavement along the length direction of a culvert, and constructing a distance control guide rail on the pavement; butting the formwork trolleys to manufacture the guide rail; and driving the formwork trolleys into or hanging the distance control guide rail. And a sealing mold assembling step: driving the template trolley to a target position, driving the integrated inner mold or the integrated outer mold to descend to abut against the concrete pavement by a chain hoist, and then sealing and covering an area enclosed by the integrated inner mold and the integrated outer mold on the same side of the template trolley by using an end template to form the sealing mold. Reinforcing and sealing the mold: enabling each pull rod to respectively penetrate through the integrated inner mold and the integrated outer mold which are positioned on the same side of the template trolley; and one end of the first threaded adjustable inclined strut is connected to the formwork trolley, and the other end of the first threaded adjustable inclined strut is connected to one of the integrated inner molds, so that the sealing mold and the formwork trolley are fixed together. The method further comprises a wall body pouring step. The construction efficiency of culvert wall construction is improved.
本发明公开了涵洞墙体建设工艺,包括浇筑地基步骤:顺着涵洞的长度方向浇筑混凝土路面,并在路面修建控距导轨。模板台车对接制成导轨步骤:将模板台车驶入或吊上控距导轨。拼装密封模具步骤:模板台车行驶至目标位置,手动葫芦驱使整体化内模或整体化外模下降至抵接混凝土路面,然后用端部模板封盖位于模板台车同一侧的整体化内模和整体化外模围合的区域内,以形成密封模具。加固密封模具步骤:将各根拉杆分别贯穿位于模板台车同一侧的整体化内模和整体化外模;将第一螺纹式可调节斜撑的一端连接于模板台车,另一端连接于其中一个整体化内模,以将密封模具与模板台车固定在一起。还包括浇筑墙体步骤。其提高了建设涵洞墙体的施工效率。
Culvert wall construction process
The invention discloses a culvert wall construction process which comprises the following steps: a foundation pouring step: pouring a concrete pavement along the length direction of a culvert, and constructing a distance control guide rail on the pavement; butting the formwork trolleys to manufacture the guide rail; and driving the formwork trolleys into or hanging the distance control guide rail. And a sealing mold assembling step: driving the template trolley to a target position, driving the integrated inner mold or the integrated outer mold to descend to abut against the concrete pavement by a chain hoist, and then sealing and covering an area enclosed by the integrated inner mold and the integrated outer mold on the same side of the template trolley by using an end template to form the sealing mold. Reinforcing and sealing the mold: enabling each pull rod to respectively penetrate through the integrated inner mold and the integrated outer mold which are positioned on the same side of the template trolley; and one end of the first threaded adjustable inclined strut is connected to the formwork trolley, and the other end of the first threaded adjustable inclined strut is connected to one of the integrated inner molds, so that the sealing mold and the formwork trolley are fixed together. The method further comprises a wall body pouring step. The construction efficiency of culvert wall construction is improved.
本发明公开了涵洞墙体建设工艺,包括浇筑地基步骤:顺着涵洞的长度方向浇筑混凝土路面,并在路面修建控距导轨。模板台车对接制成导轨步骤:将模板台车驶入或吊上控距导轨。拼装密封模具步骤:模板台车行驶至目标位置,手动葫芦驱使整体化内模或整体化外模下降至抵接混凝土路面,然后用端部模板封盖位于模板台车同一侧的整体化内模和整体化外模围合的区域内,以形成密封模具。加固密封模具步骤:将各根拉杆分别贯穿位于模板台车同一侧的整体化内模和整体化外模;将第一螺纹式可调节斜撑的一端连接于模板台车,另一端连接于其中一个整体化内模,以将密封模具与模板台车固定在一起。还包括浇筑墙体步骤。其提高了建设涵洞墙体的施工效率。
Culvert wall construction process
涵洞墙体建设工艺
HONG JUNCAI (author) / BAO HAN (author) / LIN ZHIJIE (author) / QIAN XIAOAN (author)
2023-06-30
Patent
Electronic Resource
Chinese
IPC:
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
/
E04G
SCAFFOLDING
,
Baugerüste
CULVERT WALL STRUCTURE, AND CONSTRUCTION METHOD OF CULVERT WALL
European Patent Office | 2017
|Construction structure and construction method of culvert splayed wall
European Patent Office | 2023
|Box culvert splayed wall and construction method thereof
European Patent Office | 2024
|Box culvert construction method and box culvert structure
European Patent Office | 2024
|