Synchronous construction method for tower beams of special-shaped steel tower cable-stayed bridge
The invention belongs to the technical field of bridge design and construction, and particularly relates to a special-shaped steel tower cable-stayed bridge tower beam synchronous construction method which comprises the following steps that a cable-stayed bridge main beam support, a steel tower support and a gantry crane foundation are synchronously erected; a gantry crane rail is laid on the gantry crane foundation, and a gantry crane is installed; mounting a steel-concrete combined section of the swivel steel tower and pouring concrete; installing a swivel steel tower T1 section, and testing a swivel; a cable-stayed bridge main beam is poured, and the remaining steel tower sections are spliced section by section through the gantry crane; mounting a latticed column and a latticed column jack, and vertically rotating and closing the steel tower; stay cables are installed and tensioned, and accessory structures are dismantled; and bridge deck pavement is installed, and construction of the special-shaped steel tower cable-stayed bridge is completed. The method has the beneficial effects that synchronous construction of a bridge tower and a bridge beam is achieved, and the problem that the construction period of the bridge is short is solved.
本发明属于桥梁设计施工技术领域,尤其涉及一种异形钢塔斜拉桥塔梁同步施工方法,包括以下步骤:同步搭设斜拉桥主梁支架、钢塔支架、龙门吊基础;并在龙门吊基础上铺设龙门吊轨道,安装龙门吊;安装转体钢塔钢混结合段并浇筑混凝土;安装转体钢塔T1节段,试转体;浇筑斜拉桥主梁,通过龙门吊逐节段拼装剩余钢塔节段;安装格构柱、格构柱千斤顶,对钢塔竖转合龙;安装并张拉斜拉索,拆除附属结构;安装桥面铺装,完成异形钢塔斜拉桥施工。本发明的有益效果是:实现了桥梁塔、梁同步施工,解决了桥梁施工工期紧的难题。
Synchronous construction method for tower beams of special-shaped steel tower cable-stayed bridge
The invention belongs to the technical field of bridge design and construction, and particularly relates to a special-shaped steel tower cable-stayed bridge tower beam synchronous construction method which comprises the following steps that a cable-stayed bridge main beam support, a steel tower support and a gantry crane foundation are synchronously erected; a gantry crane rail is laid on the gantry crane foundation, and a gantry crane is installed; mounting a steel-concrete combined section of the swivel steel tower and pouring concrete; installing a swivel steel tower T1 section, and testing a swivel; a cable-stayed bridge main beam is poured, and the remaining steel tower sections are spliced section by section through the gantry crane; mounting a latticed column and a latticed column jack, and vertically rotating and closing the steel tower; stay cables are installed and tensioned, and accessory structures are dismantled; and bridge deck pavement is installed, and construction of the special-shaped steel tower cable-stayed bridge is completed. The method has the beneficial effects that synchronous construction of a bridge tower and a bridge beam is achieved, and the problem that the construction period of the bridge is short is solved.
本发明属于桥梁设计施工技术领域,尤其涉及一种异形钢塔斜拉桥塔梁同步施工方法,包括以下步骤:同步搭设斜拉桥主梁支架、钢塔支架、龙门吊基础;并在龙门吊基础上铺设龙门吊轨道,安装龙门吊;安装转体钢塔钢混结合段并浇筑混凝土;安装转体钢塔T1节段,试转体;浇筑斜拉桥主梁,通过龙门吊逐节段拼装剩余钢塔节段;安装格构柱、格构柱千斤顶,对钢塔竖转合龙;安装并张拉斜拉索,拆除附属结构;安装桥面铺装,完成异形钢塔斜拉桥施工。本发明的有益效果是:实现了桥梁塔、梁同步施工,解决了桥梁施工工期紧的难题。
Synchronous construction method for tower beams of special-shaped steel tower cable-stayed bridge
一种异形钢塔斜拉桥塔梁同步施工方法
LIU XIAOMIN (author) / XIE PENGLIN (author) / ZHOU JUNLONG (author) / CAO HAIQING (author) / LI LINTING (author) / ZENG YINYONG (author) / ZHAO LEI (author) / LI BING (author) / LI XIAOPENG (author) / ZHAO XU (author)
2023-07-07
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Synchronous construction method for tower beams of short-tower cable-stayed bridge
European Patent Office | 2021
|European Patent Office | 2023
|Special-shaped landscape steel arch main tower of cable-stayed bridge and construction method
European Patent Office | 2024
|Main tower hoisting method of special-shaped space tower curve cable-stayed bridge
European Patent Office | 2023
|