Special-shaped metal composite roof construction method
The invention provides a special-shaped metal composite roof construction method. The special-shaped metal composite roof construction method comprises the following specific steps that S1, construction preparation is conducted; s2, measuring and positioning; s3, main and secondary wingceltis bar keels are constructed; s4, mounting the perforated profiled steel sheet; s5, heat preservation rock wool board construction; s6, gutter construction; s7, construction of the TPO waterproof coiled material; s8, surface layer keels are spliced and hoisted; and S9, the aluminum veneer is installed. According to the method, assembly type installation is adopted, a large amount of hoisting cost is saved, welding difficulty and workload are greatly reduced, the safety working condition and quality level of construction are obviously improved, the whole construction process is assisted by an informatization technology, material loss is effectively reduced, aluminum plate production and steel framework construction are conducted synchronously, and the construction period is greatly shortened.
本发明提供一种异形金属复合屋面施工方法,包括以下具体步骤:S1、施工准备;S2、测量定位;S3、主、次檀条龙骨施工;S4、穿孔压型钢板安装;S5、保温岩棉板施工;S6、天沟施工;S7、TPO防水卷材施工;S8、面层龙骨拼接、吊装;S9:铝单板安装。该方法采用装配式安装,节省大量吊装费,焊接难度和工作量大幅减少,施工的安全工况和质量水平明显提高,整个施工过程采用信息化技术辅助,有效降低材料损耗,铝板生产与钢骨架施工同步进行,大幅缩短工期。
Special-shaped metal composite roof construction method
The invention provides a special-shaped metal composite roof construction method. The special-shaped metal composite roof construction method comprises the following specific steps that S1, construction preparation is conducted; s2, measuring and positioning; s3, main and secondary wingceltis bar keels are constructed; s4, mounting the perforated profiled steel sheet; s5, heat preservation rock wool board construction; s6, gutter construction; s7, construction of the TPO waterproof coiled material; s8, surface layer keels are spliced and hoisted; and S9, the aluminum veneer is installed. According to the method, assembly type installation is adopted, a large amount of hoisting cost is saved, welding difficulty and workload are greatly reduced, the safety working condition and quality level of construction are obviously improved, the whole construction process is assisted by an informatization technology, material loss is effectively reduced, aluminum plate production and steel framework construction are conducted synchronously, and the construction period is greatly shortened.
本发明提供一种异形金属复合屋面施工方法,包括以下具体步骤:S1、施工准备;S2、测量定位;S3、主、次檀条龙骨施工;S4、穿孔压型钢板安装;S5、保温岩棉板施工;S6、天沟施工;S7、TPO防水卷材施工;S8、面层龙骨拼接、吊装;S9:铝单板安装。该方法采用装配式安装,节省大量吊装费,焊接难度和工作量大幅减少,施工的安全工况和质量水平明显提高,整个施工过程采用信息化技术辅助,有效降低材料损耗,铝板生产与钢骨架施工同步进行,大幅缩短工期。
Special-shaped metal composite roof construction method
一种异形金属复合屋面施工方法
LIU YONG (author) / YANG HAODONG (author) / LIU HONG (author) / CHEN YONGHONG (author) / PAN HONGXING (author) / TU GANGYAO (author)
2023-07-21
Patent
Electronic Resource
Chinese
Melon-rind-shaped special-shaped hyperbolic metal roof construction method
European Patent Office | 2021
|Special-shaped adjustable metal roof system and construction method
European Patent Office | 2023
|Curved special-shaped metal roof of stadium and construction method
European Patent Office | 2024
|Overall construction method for special-shaped cornice of metal roof
European Patent Office | 2024
|Special-shaped prefabricated inclined roof panel construction method
European Patent Office | 2022
|