A platform for research: civil engineering, architecture and urbanism
Slotting-free installation method for small kerb
The invention relates to the technical field of municipal engineering, in particular to a small curbstone grooving-free mounting method which comprises the following steps: positioning a non-motor vehicle road curbstone position and marking, placing channel steel along a mark, reinforcing a joint of the channel steel, brushing a release agent on the channel steel, performing non-motor vehicle road cement stabilized macadam construction, and maintaining for 7 days. The method comprises the following steps: transferring channel steel on the outer side of a non-motorized vehicle lane to a curbstone position on the outer side of a sidewalk, cleaning the surface of the channel steel, brushing a release agent, rotating the channel steel on the inner side of the non-motorized vehicle lane to the inner side of the sidewalk, brushing the release agent, paving cement permeable cement stabilized macadam of the sidewalk, maintaining for 7 days, dismantling the channel steel, cleaning sundries, and pouring cement concrete. Curing for 7 days, mounting curbstones, and constructing a non-motorized vehicle lane asphalt concrete surface layer and sidewalk bricks. Cutting and planing are not needed after the base layer is paved, the labor intensity is low, the material cost is saved, and air pollution caused by cutting and planing is prevented.
本发明涉及市政工程技术领域,特别是涉及一种小型路边石免开槽安装方法,定位非机动车道路边石位置并做好标记,沿标记摆放槽钢,槽钢的接头加固,槽钢涂刷脱模剂,进行非机动车道水泥稳定碎石施工,养护7天,将非机动车道外侧槽钢转运到人行道外侧路边石位置,清理好槽钢表面,并涂刷脱模剂,非机动车道内侧槽钢旋转至人行道内侧,并涂刷脱模剂,然后摊铺人行道水泥透水水泥稳定碎石,养护7天,拆除槽钢,清理杂物后浇筑水泥混凝土,养护7天后安装路边石,进行非机动车道沥青混凝土面层以及人行道道砖施工。本发明在基层摊铺完成后不用切刨,劳动强度低,节省材料成本,并防止出现切刨造成的大气污染。
Slotting-free installation method for small kerb
The invention relates to the technical field of municipal engineering, in particular to a small curbstone grooving-free mounting method which comprises the following steps: positioning a non-motor vehicle road curbstone position and marking, placing channel steel along a mark, reinforcing a joint of the channel steel, brushing a release agent on the channel steel, performing non-motor vehicle road cement stabilized macadam construction, and maintaining for 7 days. The method comprises the following steps: transferring channel steel on the outer side of a non-motorized vehicle lane to a curbstone position on the outer side of a sidewalk, cleaning the surface of the channel steel, brushing a release agent, rotating the channel steel on the inner side of the non-motorized vehicle lane to the inner side of the sidewalk, brushing the release agent, paving cement permeable cement stabilized macadam of the sidewalk, maintaining for 7 days, dismantling the channel steel, cleaning sundries, and pouring cement concrete. Curing for 7 days, mounting curbstones, and constructing a non-motorized vehicle lane asphalt concrete surface layer and sidewalk bricks. Cutting and planing are not needed after the base layer is paved, the labor intensity is low, the material cost is saved, and air pollution caused by cutting and planing is prevented.
本发明涉及市政工程技术领域,特别是涉及一种小型路边石免开槽安装方法,定位非机动车道路边石位置并做好标记,沿标记摆放槽钢,槽钢的接头加固,槽钢涂刷脱模剂,进行非机动车道水泥稳定碎石施工,养护7天,将非机动车道外侧槽钢转运到人行道外侧路边石位置,清理好槽钢表面,并涂刷脱模剂,非机动车道内侧槽钢旋转至人行道内侧,并涂刷脱模剂,然后摊铺人行道水泥透水水泥稳定碎石,养护7天,拆除槽钢,清理杂物后浇筑水泥混凝土,养护7天后安装路边石,进行非机动车道沥青混凝土面层以及人行道道砖施工。本发明在基层摊铺完成后不用切刨,劳动强度低,节省材料成本,并防止出现切刨造成的大气污染。
Slotting-free installation method for small kerb
小型路边石免开槽安装方法
XU YANPENG (author) / CHEN ZHIYONG (author) / DONG SHULIN (author) / DING YANJIE (author)
2023-08-15
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE