Floor construction method for beamless logistics storage plant
The invention discloses a floor construction method for a beamless logistics storage plant, and relates to the technical field of building construction, and the floor construction method comprises the following steps: reserving a construction joint at the axis position of a floor, and measuring and setting a reference line with a preset width at each foundation column; concrete cushion layer pouring is conducted in the soil filling range between the bearing platforms in the first-layer beam plate construction process; reinforcing steel bars connected with a floor raft plate are installed in the bearing platform construction process; laying and installing cushion layer reinforcing steel bars according to design and specification requirements; the periphery of the terrace is installed and fixed through formworks of the preset specification, and partition formworks are installed and fixed according to the reserved construction joints, and cement soil of the preset specification is poured; carrying out slurry extraction operation when the concrete is preliminarily solidified according to a preset standard, and carrying out secondary scraping by virtue of a manual scraping lever; and plastering, grinding and polishing the stricken concrete. According to the construction method provided by the invention, the structural terrace can be flexibly organized and arranged without being influenced by the construction of the upper main body structure.
本发明公开了一种用于无梁物流仓储厂房的地坪施工方法,涉及建筑施工技术领域,包括步骤:在地坪轴线位置预留施工缝,并在各基柱处测量并设置预设宽度的基准线;在首层梁板施工过程中对承台间填土范围内进行混凝土垫层浇筑;在承台施工过程中安装与地坪筏板连接的钢筋;根据设计及规范要求进行垫层钢筋的铺设安装;采用预设规格的模板进行地坪周边的安装固定,并根据预留施工缝进行分区模板的安装固定预设规格水泥土的浇筑;根据预设达标标准在混凝土初步凝固时进行提浆操作,并通过人工刮杠进行二次刮平;对刮平后的混凝土进行抹面及打磨抛光操作。本发明提出的施工方法,结构地坪能够机动灵活的组织安排而不受上部主体结构的施工影响。
Floor construction method for beamless logistics storage plant
The invention discloses a floor construction method for a beamless logistics storage plant, and relates to the technical field of building construction, and the floor construction method comprises the following steps: reserving a construction joint at the axis position of a floor, and measuring and setting a reference line with a preset width at each foundation column; concrete cushion layer pouring is conducted in the soil filling range between the bearing platforms in the first-layer beam plate construction process; reinforcing steel bars connected with a floor raft plate are installed in the bearing platform construction process; laying and installing cushion layer reinforcing steel bars according to design and specification requirements; the periphery of the terrace is installed and fixed through formworks of the preset specification, and partition formworks are installed and fixed according to the reserved construction joints, and cement soil of the preset specification is poured; carrying out slurry extraction operation when the concrete is preliminarily solidified according to a preset standard, and carrying out secondary scraping by virtue of a manual scraping lever; and plastering, grinding and polishing the stricken concrete. According to the construction method provided by the invention, the structural terrace can be flexibly organized and arranged without being influenced by the construction of the upper main body structure.
本发明公开了一种用于无梁物流仓储厂房的地坪施工方法,涉及建筑施工技术领域,包括步骤:在地坪轴线位置预留施工缝,并在各基柱处测量并设置预设宽度的基准线;在首层梁板施工过程中对承台间填土范围内进行混凝土垫层浇筑;在承台施工过程中安装与地坪筏板连接的钢筋;根据设计及规范要求进行垫层钢筋的铺设安装;采用预设规格的模板进行地坪周边的安装固定,并根据预留施工缝进行分区模板的安装固定预设规格水泥土的浇筑;根据预设达标标准在混凝土初步凝固时进行提浆操作,并通过人工刮杠进行二次刮平;对刮平后的混凝土进行抹面及打磨抛光操作。本发明提出的施工方法,结构地坪能够机动灵活的组织安排而不受上部主体结构的施工影响。
Floor construction method for beamless logistics storage plant
一种用于无梁物流仓储厂房的地坪施工方法
ZHANG ZHIHONG (author) / WANG PENG (author) / CHENG YOUKUI (author) / MA YONGQIANG (author) / LI BOYU (author)
2023-08-25
Patent
Electronic Resource
Chinese
IPC:
E04F
FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
,
Ausbau von Bauwerken, z.B. Treppen, Fußböden
Beamless floor structure with hyperbolic arch shells and construction method thereof
European Patent Office | 2020
|Beamless reinforced concrete ceiling construction
Engineering Index Backfile | 1914
|Construction method for super high-rise post-tensioned bonded prestressed beamless floor slab
European Patent Office | 2021
|Analysis of resistance to punching shear of beamless reinforced concrete floor slabs
British Library Conference Proceedings | 2004
|