Construction method for tube well dewatering
The invention belongs to the technical field of underground drainage construction, and particularly relates to a tube well dewatering construction method, which comprises the following steps of: paving an operation platform by adopting earthwork, and compacting and leveling by using an excavator; the center of a well site is determined, a circle is made with the diameter of 1100 mm of the center of the well site as the diameter, a well opening is downwards formed, and a pile casing is placed at the well opening; a lime line mark is sprayed at the preset position of the drilling machine, the drilling machine is driven to the lime line mark position, and the perpendicularity of a drill rod and a mast of the drilling machine is adjusted and locked; drilling operation is conducted through the drilling machine; checking a final hole and cleaning the bottom of the hole; preparing a well pipe by using a metal coil pipe; placing a well casing; sand and gravel materials are filled between the well casing and the soil wall, and the position 1.50 m close to the well mouth is sealed with clay; and water pumping is started after well completion construction is finished. The well casing preparation time can be shortened, construction is convenient, and the drainage efficiency is improved.
本发明属于地下排水施工技术领域,尤其涉及一种管井降水的施工方法,包括采用土方铺筑操作平台,并用挖掘机压实、找平;确定井位点中心,并以井位点中心1100mm为直径作圆,向下开井口,在所述井口放护筒;在钻机预设位置洒白灰线标记,将钻机开至白灰线标记位置,调整钻机的钻杆、桅杆的竖直度并锁定;利用所述钻机进行钻孔作业;进行终孔检查并对孔底进行清理;使用金属卷管制备井管;安放井管;在井管与土壁间填充砂砾料,接近井口1.50m处,用粘土封严;成井施工结束,开始抽水。本发明可以减少井管准备时间,施工方便,提高排水效率。
Construction method for tube well dewatering
The invention belongs to the technical field of underground drainage construction, and particularly relates to a tube well dewatering construction method, which comprises the following steps of: paving an operation platform by adopting earthwork, and compacting and leveling by using an excavator; the center of a well site is determined, a circle is made with the diameter of 1100 mm of the center of the well site as the diameter, a well opening is downwards formed, and a pile casing is placed at the well opening; a lime line mark is sprayed at the preset position of the drilling machine, the drilling machine is driven to the lime line mark position, and the perpendicularity of a drill rod and a mast of the drilling machine is adjusted and locked; drilling operation is conducted through the drilling machine; checking a final hole and cleaning the bottom of the hole; preparing a well pipe by using a metal coil pipe; placing a well casing; sand and gravel materials are filled between the well casing and the soil wall, and the position 1.50 m close to the well mouth is sealed with clay; and water pumping is started after well completion construction is finished. The well casing preparation time can be shortened, construction is convenient, and the drainage efficiency is improved.
本发明属于地下排水施工技术领域,尤其涉及一种管井降水的施工方法,包括采用土方铺筑操作平台,并用挖掘机压实、找平;确定井位点中心,并以井位点中心1100mm为直径作圆,向下开井口,在所述井口放护筒;在钻机预设位置洒白灰线标记,将钻机开至白灰线标记位置,调整钻机的钻杆、桅杆的竖直度并锁定;利用所述钻机进行钻孔作业;进行终孔检查并对孔底进行清理;使用金属卷管制备井管;安放井管;在井管与土壁间填充砂砾料,接近井口1.50m处,用粘土封严;成井施工结束,开始抽水。本发明可以减少井管准备时间,施工方便,提高排水效率。
Construction method for tube well dewatering
一种管井降水的施工方法
ZHANG BAIPING (author) / YUAN GUANGLIN (author) / HE BANGFU (author)
2023-09-05
Patent
Electronic Resource
Chinese
Dewatering well construction method, dewatering well and dewatering well system
European Patent Office | 2023
|Tube well dewatering well completion device and tube well dewatering well completion method
European Patent Office | 2022
|Construction method for vacuum tube well dewatering system
European Patent Office | 2015
|Tube well and light well point combined dewatering construction method
European Patent Office | 2022
|Mounting device for tube well filter tube in tube well dewatering construction
European Patent Office | 2024
|