Large-space suspended ceiling conversion layer construction process
The invention provides a large-space suspended ceiling conversion layer construction technology. The large-space suspended ceiling conversion layer construction technology comprises the following steps that firstly, a scaffold is erected; step 2, surveying and setting out; step 3, welding and mounting the steel framework; and 4, checking and accepting. According to the construction process, the steel skeleton grid is connected with the original building structure layer, and a secondary structure layer for mounting keels of a ceiling system is formed at a proper height position, so that a mounting conversion supporting system is formed, and the ceiling construction quality meets the requirements of design and construction specifications; the large-space suspended ceiling can be fixed according to the standard requirement, and the distance meets the construction standard requirement; the mounting problem of the special-shaped arc-shaped suspended ceiling can be solved; the construction difficulty is reduced, and the construction progress and quality are ensured.
本发明提供了一种大空间吊顶转换层施工工艺,包括以下步骤:步骤一,脚手架搭设;步骤二,测量放线;步骤三,钢骨架焊接安装;步骤四,检查验收。本发明施工工艺通过钢骨架网格与原建筑结构层连接,在适当高度位置形成可以供吊顶系统安装龙骨的次结构层,从而形成安装转换支撑系统,使吊顶施工质量达到设计、施工规范的要求;能解决大空间吊顶达到按规范要求固定,间距满足施工规范要求问题;能解决异形弧形吊顶安装问题;降低施工难度,保证施工进度及质量。
Large-space suspended ceiling conversion layer construction process
The invention provides a large-space suspended ceiling conversion layer construction technology. The large-space suspended ceiling conversion layer construction technology comprises the following steps that firstly, a scaffold is erected; step 2, surveying and setting out; step 3, welding and mounting the steel framework; and 4, checking and accepting. According to the construction process, the steel skeleton grid is connected with the original building structure layer, and a secondary structure layer for mounting keels of a ceiling system is formed at a proper height position, so that a mounting conversion supporting system is formed, and the ceiling construction quality meets the requirements of design and construction specifications; the large-space suspended ceiling can be fixed according to the standard requirement, and the distance meets the construction standard requirement; the mounting problem of the special-shaped arc-shaped suspended ceiling can be solved; the construction difficulty is reduced, and the construction progress and quality are ensured.
本发明提供了一种大空间吊顶转换层施工工艺,包括以下步骤:步骤一,脚手架搭设;步骤二,测量放线;步骤三,钢骨架焊接安装;步骤四,检查验收。本发明施工工艺通过钢骨架网格与原建筑结构层连接,在适当高度位置形成可以供吊顶系统安装龙骨的次结构层,从而形成安装转换支撑系统,使吊顶施工质量达到设计、施工规范的要求;能解决大空间吊顶达到按规范要求固定,间距满足施工规范要求问题;能解决异形弧形吊顶安装问题;降低施工难度,保证施工进度及质量。
Large-space suspended ceiling conversion layer construction process
一种大空间吊顶转换层施工工艺
JIANG XIAOBING (author) / ZOU XIAONIU (author) / XIA JIQING (author)
2023-09-15
Patent
Electronic Resource
Chinese
Construction method for suspended ceiling conversion layer
European Patent Office | 2024
|European Patent Office | 2024
|Construction method of large-span steel beam roof suspended ceiling conversion layer
European Patent Office | 2023
|