Construction method of independent column under hilly land shape
The invention provides a construction method for an independent column under a hilly terrain, and belongs to the technical field of building construction.The construction method for the independent column under the hilly terrain comprises the following steps that the construction position and depth of the independent column are determined; determining the longitudinal platform size of the independent column construction platform; listing an accessory list and a component list; the independent column templates and accessories in the list are machined and completed; the independent column formworks, the independent column formwork accessories and the independent column construction platform components are transported to a construction site to be classified and stacked; the foundation is treated; the independent column construction platform is installed; construction splicing of the independent column formworks is conducted; elevation axis rechecking and independent column perpendicularity checking are carried out; concrete is poured into the spliced independent column formworks, and concrete curing is completed; the independent column formwork is dismantled; cleaning work is carried out; the relation between the size and the bearing capacity of the independent column construction platform can reach the optimal ratio, the independent column construction quality is improved to the maximum extent, and the construction period is shortened.
本发明提供了一种山坡地形下独立柱施工方法,属于建筑施工技术领域,该山坡地形下独立柱施工方法,包括以下步骤:确定独立柱施工的位置和深度;确定所述独立柱施工平台的纵向的平台尺寸;列出配件清单以及构件清单;加工完成清单中的独立柱模板和配件;将独立柱模板、独立柱模板配件以及所述独立柱施工平台构件运输到施工现场分类堆放;对地基进行处理;安装所述独立柱施工平台;进行独立柱模板的施工拼接;进行标高轴线复核、独立柱垂直度检查;向拼接好的独立柱模板浇筑混凝土并完成混凝土的养护;拆除独立柱模板;进行清理工作;本发明能够使独立柱施工平台的尺寸和承重能力的关系达到最优比,最大限度提高独立柱施工的质量、降低施工周期。
Construction method of independent column under hilly land shape
The invention provides a construction method for an independent column under a hilly terrain, and belongs to the technical field of building construction.The construction method for the independent column under the hilly terrain comprises the following steps that the construction position and depth of the independent column are determined; determining the longitudinal platform size of the independent column construction platform; listing an accessory list and a component list; the independent column templates and accessories in the list are machined and completed; the independent column formworks, the independent column formwork accessories and the independent column construction platform components are transported to a construction site to be classified and stacked; the foundation is treated; the independent column construction platform is installed; construction splicing of the independent column formworks is conducted; elevation axis rechecking and independent column perpendicularity checking are carried out; concrete is poured into the spliced independent column formworks, and concrete curing is completed; the independent column formwork is dismantled; cleaning work is carried out; the relation between the size and the bearing capacity of the independent column construction platform can reach the optimal ratio, the independent column construction quality is improved to the maximum extent, and the construction period is shortened.
本发明提供了一种山坡地形下独立柱施工方法,属于建筑施工技术领域,该山坡地形下独立柱施工方法,包括以下步骤:确定独立柱施工的位置和深度;确定所述独立柱施工平台的纵向的平台尺寸;列出配件清单以及构件清单;加工完成清单中的独立柱模板和配件;将独立柱模板、独立柱模板配件以及所述独立柱施工平台构件运输到施工现场分类堆放;对地基进行处理;安装所述独立柱施工平台;进行独立柱模板的施工拼接;进行标高轴线复核、独立柱垂直度检查;向拼接好的独立柱模板浇筑混凝土并完成混凝土的养护;拆除独立柱模板;进行清理工作;本发明能够使独立柱施工平台的尺寸和承重能力的关系达到最优比,最大限度提高独立柱施工的质量、降低施工周期。
Construction method of independent column under hilly land shape
一种山坡地形下独立柱施工方法
XU YUEFENG (author) / WANG BAODONG (author) / LI DEWEN (author) / WANG LIBIN (author) / ZHENG ZHIQIANG (author)
2023-10-03
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Building supporting structure applied to hilly land shape
European Patent Office | 2023
|Construction method for changing hilly land into terraced field
European Patent Office | 2022
|Land Slides in Hilly Terrain in South Assam
British Library Conference Proceedings | 2003
|