A platform for research: civil engineering, architecture and urbanism
Pier column reinforcement cage construction method
The invention discloses a pier column reinforcement cage construction method, which belongs to the field of building construction, and comprises the following steps: S1, selecting materials of a reinforcement cage according to a design drawing, and carrying out modular processing forming in a reinforcement processing factory; s2, the reinforcement cage is locally reinforced; s3, the steel reinforcement framework is transported in a segmented and blocked mode; s4, pier column reinforcement cage standard segments are subjected to pre-buried construction; and S5, the upper part of the reinforcement cage is hoisted on the basis of the step S4. According to the construction method for the pier column reinforcement cage, the bearing platform reinforcement and the pier column reinforcement can be subjected to parallel line production; the positions of the main reinforcements and the positions of the stirrups in the pier column reinforcements are accurately controlled, the construction progress and the engineering quality can be effectively improved, the construction safety is ensured, integral hoisting is performed after prefabrication is completed, the overhead working and crane working time is shortened, and the construction cost is reduced.
本发明公开了一种墩柱钢筋笼施工方法,属于建筑施工领域,包括以下步骤:S1、根据设计图纸进行钢筋笼的选材,在钢筋加工厂进行模块化加工成型;S2、对钢筋骨架进行局部加固;S3、钢筋骨架分段分块运输;S4、墩柱钢筋笼标准节段预埋施工;S5、在步骤S4的基础上吊装上部分钢筋笼。本发明采用上述的一种墩柱钢筋笼施工方法,承台钢筋与墩柱钢筋可平行流水作业;墩柱钢筋中主筋位置及箍筋位置控制精确,可以有效地提高施工进度以及工程质量,确保施工安全,预制完成后整体吊装,减少高空作业和吊车作业时间,降低施工成本。
Pier column reinforcement cage construction method
The invention discloses a pier column reinforcement cage construction method, which belongs to the field of building construction, and comprises the following steps: S1, selecting materials of a reinforcement cage according to a design drawing, and carrying out modular processing forming in a reinforcement processing factory; s2, the reinforcement cage is locally reinforced; s3, the steel reinforcement framework is transported in a segmented and blocked mode; s4, pier column reinforcement cage standard segments are subjected to pre-buried construction; and S5, the upper part of the reinforcement cage is hoisted on the basis of the step S4. According to the construction method for the pier column reinforcement cage, the bearing platform reinforcement and the pier column reinforcement can be subjected to parallel line production; the positions of the main reinforcements and the positions of the stirrups in the pier column reinforcements are accurately controlled, the construction progress and the engineering quality can be effectively improved, the construction safety is ensured, integral hoisting is performed after prefabrication is completed, the overhead working and crane working time is shortened, and the construction cost is reduced.
本发明公开了一种墩柱钢筋笼施工方法,属于建筑施工领域,包括以下步骤:S1、根据设计图纸进行钢筋笼的选材,在钢筋加工厂进行模块化加工成型;S2、对钢筋骨架进行局部加固;S3、钢筋骨架分段分块运输;S4、墩柱钢筋笼标准节段预埋施工;S5、在步骤S4的基础上吊装上部分钢筋笼。本发明采用上述的一种墩柱钢筋笼施工方法,承台钢筋与墩柱钢筋可平行流水作业;墩柱钢筋中主筋位置及箍筋位置控制精确,可以有效地提高施工进度以及工程质量,确保施工安全,预制完成后整体吊装,减少高空作业和吊车作业时间,降低施工成本。
Pier column reinforcement cage construction method
墩柱钢筋笼施工方法
WANG KANGYU (author) / QIU ZILIANG (author) / CHEN XINKAI (author) / ZHU JIAYU (author) / YE JIAHUAN (author)
2023-10-24
Patent
Electronic Resource
Chinese
Prefabricated pier column reinforcement cage and integral hoisting construction method thereof
European Patent Office | 2023
|Pier column reinforcement cage protection layer device and comprehensive construction method
European Patent Office | 2022
|Pier column reinforcement cage binding jig frame and bent cap construction method
European Patent Office | 2024
|Pier column reinforcement cage internal lofting prism device
European Patent Office | 2023
|European Patent Office | 2024
|