Fabricated column-beam-wall integrated building house with ultra-low energy consumption
The invention discloses a fabricated ultra-low-energy-consumption column-beam-wall integrated building house, and belongs to the technical field of building engineering. The problems that a traditional building system seriously wastes resources and energy consumption, does not have good flexibility in the construction process, and is difficult to transform and adapt to change requirements are solved. Two first wallboard assemblies are connected to form a column body, a beam body and a wall body, each first wallboard assembly comprises a heat preservation board, an inner wallboard and an outer wallboard, the heat preservation boards are arranged between the inner wallboards and the outer wallboards, supporting beams are arranged on the outer wallboards, the outer wallboards and the supporting beams are integrally machined and formed, and the bottoms of the first wallboard assemblies are arranged in a ground groove. A pouring hole is formed in the bottom of the first wall plate assembly, the end of the first wall plate assembly is connected with the lifting layer wall plate assembly through a positioning insertion piece, and a shed plate is connected between the first wall plate assembly and the lifting layer wall plate assembly. According to the column-beam-wall integrated frame building system, the construction process can be reduced, the construction period is short, the construction cost is low, and the delivery time is short.
一种装配式超低能耗柱梁墙一体化建筑房屋,属于建筑工程技术领域。本发明解决了传统建筑体系对于资源和能耗的浪费较为严重,且在施工过程中不具备较好的灵活性,难以进行改造和适应变化需求的问题。本发明的两个第一墙板组件连接后形成柱体、梁体和墙体,第一墙板组件包括保温板、内墙板和外墙板,保温板设置内墙板和外墙板之间,外墙板上设置有支撑梁,外墙板与支撑梁一体加工成型,第一墙板组件的底部设置在地槽内,第一墙板组件的底部加工有浇注孔,第一墙板组件的端部通过定位插件与升层墙板组件连接,第一墙板组件与升层墙板组件之间连接有棚板。本发明的柱梁墙一体化框架建筑体系可减少施工过程,施工周期短,施工成本低且交付时间短。
Fabricated column-beam-wall integrated building house with ultra-low energy consumption
The invention discloses a fabricated ultra-low-energy-consumption column-beam-wall integrated building house, and belongs to the technical field of building engineering. The problems that a traditional building system seriously wastes resources and energy consumption, does not have good flexibility in the construction process, and is difficult to transform and adapt to change requirements are solved. Two first wallboard assemblies are connected to form a column body, a beam body and a wall body, each first wallboard assembly comprises a heat preservation board, an inner wallboard and an outer wallboard, the heat preservation boards are arranged between the inner wallboards and the outer wallboards, supporting beams are arranged on the outer wallboards, the outer wallboards and the supporting beams are integrally machined and formed, and the bottoms of the first wallboard assemblies are arranged in a ground groove. A pouring hole is formed in the bottom of the first wall plate assembly, the end of the first wall plate assembly is connected with the lifting layer wall plate assembly through a positioning insertion piece, and a shed plate is connected between the first wall plate assembly and the lifting layer wall plate assembly. According to the column-beam-wall integrated frame building system, the construction process can be reduced, the construction period is short, the construction cost is low, and the delivery time is short.
一种装配式超低能耗柱梁墙一体化建筑房屋,属于建筑工程技术领域。本发明解决了传统建筑体系对于资源和能耗的浪费较为严重,且在施工过程中不具备较好的灵活性,难以进行改造和适应变化需求的问题。本发明的两个第一墙板组件连接后形成柱体、梁体和墙体,第一墙板组件包括保温板、内墙板和外墙板,保温板设置内墙板和外墙板之间,外墙板上设置有支撑梁,外墙板与支撑梁一体加工成型,第一墙板组件的底部设置在地槽内,第一墙板组件的底部加工有浇注孔,第一墙板组件的端部通过定位插件与升层墙板组件连接,第一墙板组件与升层墙板组件之间连接有棚板。本发明的柱梁墙一体化框架建筑体系可减少施工过程,施工周期短,施工成本低且交付时间短。
Fabricated column-beam-wall integrated building house with ultra-low energy consumption
一种装配式超低能耗柱梁墙一体化建筑房屋
TIAN YE (author) / TIAN XIANYOU (author) / LI YAN (author)
2023-10-24
Patent
Electronic Resource
Chinese
Fabricated column-beam-wall integrated building house with ultra-low energy consumption
European Patent Office | 2024
|Fabricated concrete beam-column joint with replaceable energy consumption component
European Patent Office | 2024
|Preparation method of ultra-low-energy-consumption laminated shear wall plate in fabricated building