Novel adding process for prefabricated berthing component of built wharf
The invention discloses a novel adding process for a prefabricated berthing component of a built wharf. The novel adding process comprises the following steps: (1) repairing: repairing a concrete cross beam of the built wharf; (2) steel bar planting: drilling holes in the repaired concrete cross beam, planting steel bars in the drilled holes, and injecting anchoring glue into the steel bars and the holes to fix the steel bars and the concrete cross beam; (3) mounting of the prefabricated berthing component: hoisting the prefabricated berthing component to the reinforcing steel bars by using hoisting equipment, keeping the reinforcing steel bars and the prefabricated berthing component at the same height, and then welding the prefabricated berthing component and the reinforcing steel bars; and (4) concrete pouring is conducted, specifically, formwork erecting is conducted on the welding positions of the steel bars and the prefabricated berthing members, concrete pouring is conducted at the formwork erecting positions, formwork dismounting is conducted after the concrete is solidified, and the prefabricated berthing members are additionally installed. The installation convenience of the prefabricated berthing component is improved, and the installation cost is reduced.
本发明公开了一种新型已建码头预制靠船构件的加装工艺,其步骤为:①修复:对已建码头的混凝土横梁处进行修复;②植筋:在修复好的混凝土横梁上钻孔,并在钻孔处植入钢筋,同时在钢筋和孔位处注入锚固胶,使钢筋和混凝土横梁固定;③预制靠船构件的安装:利用吊装设备将预制靠船构件吊装置钢筋处,并且使得钢筋和预制靠船构件保持统一高度,然后再将预制靠船构件和钢筋进行焊接;④混凝土浇筑:将钢筋和预制靠船构件的焊接处支模,并接在支模处浇筑混凝土,待混凝土凝固之后拆模,完成预制靠船构件的加装。本发明提高了预制靠船构件加装的便利性,降低了加装成本。
Novel adding process for prefabricated berthing component of built wharf
The invention discloses a novel adding process for a prefabricated berthing component of a built wharf. The novel adding process comprises the following steps: (1) repairing: repairing a concrete cross beam of the built wharf; (2) steel bar planting: drilling holes in the repaired concrete cross beam, planting steel bars in the drilled holes, and injecting anchoring glue into the steel bars and the holes to fix the steel bars and the concrete cross beam; (3) mounting of the prefabricated berthing component: hoisting the prefabricated berthing component to the reinforcing steel bars by using hoisting equipment, keeping the reinforcing steel bars and the prefabricated berthing component at the same height, and then welding the prefabricated berthing component and the reinforcing steel bars; and (4) concrete pouring is conducted, specifically, formwork erecting is conducted on the welding positions of the steel bars and the prefabricated berthing members, concrete pouring is conducted at the formwork erecting positions, formwork dismounting is conducted after the concrete is solidified, and the prefabricated berthing members are additionally installed. The installation convenience of the prefabricated berthing component is improved, and the installation cost is reduced.
本发明公开了一种新型已建码头预制靠船构件的加装工艺,其步骤为:①修复:对已建码头的混凝土横梁处进行修复;②植筋:在修复好的混凝土横梁上钻孔,并在钻孔处植入钢筋,同时在钢筋和孔位处注入锚固胶,使钢筋和混凝土横梁固定;③预制靠船构件的安装:利用吊装设备将预制靠船构件吊装置钢筋处,并且使得钢筋和预制靠船构件保持统一高度,然后再将预制靠船构件和钢筋进行焊接;④混凝土浇筑:将钢筋和预制靠船构件的焊接处支模,并接在支模处浇筑混凝土,待混凝土凝固之后拆模,完成预制靠船构件的加装。本发明提高了预制靠船构件加装的便利性,降低了加装成本。
Novel adding process for prefabricated berthing component of built wharf
一种新型已建码头预制靠船构件的加装工艺
ZHU MING (author) / ZHAN MINGXU (author) / YU HONGHAI (author) / LUAN JUNLIN (author) / WANG HAO (author) / WANG YU (author) / GU YI (author) / CHEN TIANLIANG (author) / WANG JIANQIANG (author)
2023-11-24
Patent
Electronic Resource
Chinese
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
Wharf berthing prefabricated part supporting system and setting method
European Patent Office | 2023
|