Construction method of combined section steel super-long triangular outer protection frame for high-rise fabricated building
The invention discloses a construction method of a combined section steel super-long triangular outer protective frame for a high-rise fabricated building, and relates to the technical field of building construction.The construction method comprises the following steps that S1, a double-I-steel stand column is arranged at the position of an indoor balcony, the top of the double-I-steel stand column is connected with a structural beam, and the bottom of the double-I-steel stand column is connected with a fixing frame; s2, after the double-I-steel stand column is installed, the super-long combined type steel triangular frame is connected with the double-I-steel stand column; and S3, after the ultra-long combined type steel triangular frame is installed, the outer protection frame is erected along the floor height, wall connecting pieces are arranged in each layer of balcony to be connected with the outer protection frame, and the protection frame is connected with the ultra-long combined type steel triangular frame through connecting devices. According to the construction method, the difficult problem of construction of the outer protection frame foundation of a special part can be solved, the problem of connection of two different construction technologies of a traditional standard tripod foundation and a floor scaffold is avoided, the construction difficulty is further reduced, and the construction progress is accelerated.
本发明公开了一种高层装配式建筑组合型钢超长三角外防护架施工方法,涉及建筑施工技术领域,所述施工方法包括以下步骤:S1:在室内阳台位置设置双工字钢立柱,将双工字钢立柱顶部与结构梁连接,将双工字钢立柱底部与固定架连接;S2:双工字钢立柱安装完毕后,将超长组合型钢三角架与双工字钢立柱连接;S3:超长组合型钢三角架安装完毕后,将外防护架沿层高搭设,并在每层阳台内设置连墙件与外防护架的连接,防护架通过连接装置与超长组合型钢三角架连接。本发明能够解决特殊部位的外防护架基础施工的难点问题,避免传统标准型三脚架基础与落地脚手架两种不同施工工艺衔接的问题、进一步降低施工难度、加快施工进度。
Construction method of combined section steel super-long triangular outer protection frame for high-rise fabricated building
The invention discloses a construction method of a combined section steel super-long triangular outer protective frame for a high-rise fabricated building, and relates to the technical field of building construction.The construction method comprises the following steps that S1, a double-I-steel stand column is arranged at the position of an indoor balcony, the top of the double-I-steel stand column is connected with a structural beam, and the bottom of the double-I-steel stand column is connected with a fixing frame; s2, after the double-I-steel stand column is installed, the super-long combined type steel triangular frame is connected with the double-I-steel stand column; and S3, after the ultra-long combined type steel triangular frame is installed, the outer protection frame is erected along the floor height, wall connecting pieces are arranged in each layer of balcony to be connected with the outer protection frame, and the protection frame is connected with the ultra-long combined type steel triangular frame through connecting devices. According to the construction method, the difficult problem of construction of the outer protection frame foundation of a special part can be solved, the problem of connection of two different construction technologies of a traditional standard tripod foundation and a floor scaffold is avoided, the construction difficulty is further reduced, and the construction progress is accelerated.
本发明公开了一种高层装配式建筑组合型钢超长三角外防护架施工方法,涉及建筑施工技术领域,所述施工方法包括以下步骤:S1:在室内阳台位置设置双工字钢立柱,将双工字钢立柱顶部与结构梁连接,将双工字钢立柱底部与固定架连接;S2:双工字钢立柱安装完毕后,将超长组合型钢三角架与双工字钢立柱连接;S3:超长组合型钢三角架安装完毕后,将外防护架沿层高搭设,并在每层阳台内设置连墙件与外防护架的连接,防护架通过连接装置与超长组合型钢三角架连接。本发明能够解决特殊部位的外防护架基础施工的难点问题,避免传统标准型三脚架基础与落地脚手架两种不同施工工艺衔接的问题、进一步降低施工难度、加快施工进度。
Construction method of combined section steel super-long triangular outer protection frame for high-rise fabricated building
一种高层装配式建筑组合型钢超长三角外防护架施工方法
AI JIANZHONG (author) / DONG RUI (author) / LIU SHUANG (author) / JI GUIWU (author) / WANG GAOFENG (author) / YU SIHAN (author) / YANG YAZHOU (author) / LIU KEQIONG (author) / LIU SHU (author) / ZU MENGCHEN (author)
2023-11-24
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Construction method of super high-rise complex facade combined outer protection frame
European Patent Office | 2024
|Super high-rise outer frame inclined circular pipe steel column pouring construction method
European Patent Office | 2024
|Construction method for outer frame steel pipe column of super high-rise structure
European Patent Office | 2020
|Fabricated building edge protection device free of outer frame construction
European Patent Office | 2023
|Lifting frame with protection function for fabricated building outer wall construction
European Patent Office | 2020
|