Supporting platform dismantling method
The invention relates to a supporting platform dismantling method. The method comprises the steps that a steel bridge deck is fixed to the bottom end of a bearing platform; the multiple stand columns are divided into first stand columns and second stand columns, and the first stand columns and the second stand columns are arranged in a staggered mode; a cushion block at the top end of the first stand column is dismantled, and a distribution beam and a bailey beam at the top end of the first stand column are lowered to the first stand column; a cushion block at the top end of the second stand column is dismantled, and a distribution beam and a bailey beam at the top end of the second stand column are lowered to the second stand column; the bailey beams and the distribution beams are dismantled; the whole steel bridge deck slab is lowered to the first stand column and the second stand column; and the steel bridge deck slab is dismantled. The disassembling sequence of the steel bridge deck, the distribution beams and the bailey beams is changed, the bailey beams and the distribution beams are firstly disassembled, then the steel bridge deck is disassembled, and the bailey beams, the distribution beams and the steel bridge deck are all lowered to the first stand columns and the second stand columns and then disassembled, so that the hoisting and disassembling heights of the steel bridge deck, the distribution beams and the bailey beams are reduced, the disassembling mode is simple, and the disassembling efficiency is improved. And the safety is improved.
本申请涉及一种支撑平台拆除方法,其包括:将钢桥面板固定于承台底端;将多个立柱分为第一立柱和第二立柱,并使第一立柱和第二立柱交错设置;拆除第一立柱顶端垫块,并将第一立柱顶端的分配梁和贝雷梁下放至第一立柱上;拆除第二立柱顶端垫块,并将第二立柱顶端的分配梁和贝雷梁下放至第二立柱上;拆除贝雷梁和分配梁;将钢桥面板整体下放至第一立柱和第二立柱上;拆除钢桥面板。本发明改变了钢桥面板、分配梁及贝雷梁拆卸顺序,先拆除贝雷梁和分配梁,然后拆卸钢桥面板,并将贝雷梁、分配梁和钢桥面板均下放至第一立柱和第二立柱上后拆除,降低了钢桥面板、分配梁及贝雷梁吊装拆除的高度,使拆除方式简单,提高了安全性。
Supporting platform dismantling method
The invention relates to a supporting platform dismantling method. The method comprises the steps that a steel bridge deck is fixed to the bottom end of a bearing platform; the multiple stand columns are divided into first stand columns and second stand columns, and the first stand columns and the second stand columns are arranged in a staggered mode; a cushion block at the top end of the first stand column is dismantled, and a distribution beam and a bailey beam at the top end of the first stand column are lowered to the first stand column; a cushion block at the top end of the second stand column is dismantled, and a distribution beam and a bailey beam at the top end of the second stand column are lowered to the second stand column; the bailey beams and the distribution beams are dismantled; the whole steel bridge deck slab is lowered to the first stand column and the second stand column; and the steel bridge deck slab is dismantled. The disassembling sequence of the steel bridge deck, the distribution beams and the bailey beams is changed, the bailey beams and the distribution beams are firstly disassembled, then the steel bridge deck is disassembled, and the bailey beams, the distribution beams and the steel bridge deck are all lowered to the first stand columns and the second stand columns and then disassembled, so that the hoisting and disassembling heights of the steel bridge deck, the distribution beams and the bailey beams are reduced, the disassembling mode is simple, and the disassembling efficiency is improved. And the safety is improved.
本申请涉及一种支撑平台拆除方法,其包括:将钢桥面板固定于承台底端;将多个立柱分为第一立柱和第二立柱,并使第一立柱和第二立柱交错设置;拆除第一立柱顶端垫块,并将第一立柱顶端的分配梁和贝雷梁下放至第一立柱上;拆除第二立柱顶端垫块,并将第二立柱顶端的分配梁和贝雷梁下放至第二立柱上;拆除贝雷梁和分配梁;将钢桥面板整体下放至第一立柱和第二立柱上;拆除钢桥面板。本发明改变了钢桥面板、分配梁及贝雷梁拆卸顺序,先拆除贝雷梁和分配梁,然后拆卸钢桥面板,并将贝雷梁、分配梁和钢桥面板均下放至第一立柱和第二立柱上后拆除,降低了钢桥面板、分配梁及贝雷梁吊装拆除的高度,使拆除方式简单,提高了安全性。
Supporting platform dismantling method
一种支撑平台拆除方法
BAI XIAOMING (author) / ZHOU ZAIXING (author) / LIU WEI (author) / TAN HAO (author) / YU WENZHI (author) / ZHOU ZHENGZHONG (author) / HUANG PEI (author) / LI YANZHE (author) / GAO XIN (author) / GUO ZHENHUA (author)
2023-12-26
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
European Patent Office | 2022
|Dismantling equipment and dismantling method for lower supporting structure of bridge
European Patent Office | 2023
|Roof layer beam dismantling supporting structure and dismantling mode
European Patent Office | 2022
|Dismantling device and dismantling method for bent cap construction platform
European Patent Office | 2022
|