The invention relates to the technical field of bridge construction, and discloses and provides a steel trestle construction method, which comprises the following steps: construction preparation: before construction, comprehensively mastering local climate conditions, hydrological characteristics and geological conditions, dividing a to-be-constructed steel trestle into sections for construction according to a design drawing, and reasonably arranging operation in time according to a planned construction period; organizing constructors, equipment and materials to enter the field; preparing materials, measuring and calculating, and constructing; the hoisting equipment gradually constructs the follow-up beam bodies and the steel pipe piles on the built beam bodies, the procedure of building a construction platform in a river channel is avoided, construction is greatly simplified, the construction period is shortened, the construction cost is reduced, and when the steel pipe piles are designed to be in a hard stratum, the vibratory hammer is adopted for constructing the steel pipe piles, so that the construction efficiency is improved. The safety and the reliability of the steel pipe pile support are further ensured; and moreover, the construction procedures are greatly simplified, the construction period is shortened, and the construction cost is reduced.
本发明涉及桥梁施工技术领域,公开了提供的一种钢栈桥施工方法,施工准备:施工之前,全面掌握当地气候条件、水文特征、地质情况,根据设计图纸将待施工的钢栈桥划分段施工,及时根据计划工期合理安排作业,组织施工人员、设备和材料进场;材料准备,测量计算,施工搭建;吊装设备在已搭建好的梁体上对后续梁体和钢管桩进行逐步施工,避免了在河道内搭建施工平台的工序,进而大幅简化了施工,缩短了施工工期,降低了施工成本,当钢管桩设计位置为硬质地层,采用上述振动锤对钢管桩进行施工,如此,也进一步的确保了钢管桩支持的安全性和可靠性;并且,还大幅简化了施工工序,缩短了施工工期,降低了施工成本。
Steel trestle construction method
The invention relates to the technical field of bridge construction, and discloses and provides a steel trestle construction method, which comprises the following steps: construction preparation: before construction, comprehensively mastering local climate conditions, hydrological characteristics and geological conditions, dividing a to-be-constructed steel trestle into sections for construction according to a design drawing, and reasonably arranging operation in time according to a planned construction period; organizing constructors, equipment and materials to enter the field; preparing materials, measuring and calculating, and constructing; the hoisting equipment gradually constructs the follow-up beam bodies and the steel pipe piles on the built beam bodies, the procedure of building a construction platform in a river channel is avoided, construction is greatly simplified, the construction period is shortened, the construction cost is reduced, and when the steel pipe piles are designed to be in a hard stratum, the vibratory hammer is adopted for constructing the steel pipe piles, so that the construction efficiency is improved. The safety and the reliability of the steel pipe pile support are further ensured; and moreover, the construction procedures are greatly simplified, the construction period is shortened, and the construction cost is reduced.
本发明涉及桥梁施工技术领域,公开了提供的一种钢栈桥施工方法,施工准备:施工之前,全面掌握当地气候条件、水文特征、地质情况,根据设计图纸将待施工的钢栈桥划分段施工,及时根据计划工期合理安排作业,组织施工人员、设备和材料进场;材料准备,测量计算,施工搭建;吊装设备在已搭建好的梁体上对后续梁体和钢管桩进行逐步施工,避免了在河道内搭建施工平台的工序,进而大幅简化了施工,缩短了施工工期,降低了施工成本,当钢管桩设计位置为硬质地层,采用上述振动锤对钢管桩进行施工,如此,也进一步的确保了钢管桩支持的安全性和可靠性;并且,还大幅简化了施工工序,缩短了施工工期,降低了施工成本。
Steel trestle construction method
一种钢栈桥施工方法
LUO HUASONG (author) / KE SHUANGXUE (author) / CAO ZEZHUN (author) / ZHANG WEI (author) / LU JIANGLONG (author) / TAN LIFENG (author) / WANG XUEQIANG (author) / SHANG CAIXIA (author)
2024-01-02
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Fabricated steel trestle structure and steel trestle construction method