The invention relates to an assembly type straining beam hoisting construction method. The method comprises the steps that firstly, a straining beam is prefabricated on a construction site; 2, on-site maintenance and finished product protection of the straining beam; thirdly, pier column pile head steel bars are adjusted; 4, on-site hoisting construction of the straining beam is conducted; fifthly, reinforcing and installing pier column and tie beam joint steel bars, and installing and fixing customized steel formworks; and sixthly, joint concrete is poured, vibrated and maintained. The construction speed is increased, the process is simple, the construction efficiency is high, and the influence on the surrounding water body can be reduced to the maximum extent.
本发明涉及一种装配式系梁吊装施工方法,步骤一:系梁施工现场预制;步骤二:系梁现场养护与成品保护;步骤三:墩柱桩头钢筋调整;步骤四:系梁现场吊装施工;步骤五:墩柱与系梁节点钢筋加固与安装,定制钢模板安装固定;步骤六:节点混凝土浇筑振捣与养护。本发明加快施工建造速度,工艺简单,施工效率高,可最大程度减少对周围水体造成影响。
Fabricated straining beam hoisting construction method
The invention relates to an assembly type straining beam hoisting construction method. The method comprises the steps that firstly, a straining beam is prefabricated on a construction site; 2, on-site maintenance and finished product protection of the straining beam; thirdly, pier column pile head steel bars are adjusted; 4, on-site hoisting construction of the straining beam is conducted; fifthly, reinforcing and installing pier column and tie beam joint steel bars, and installing and fixing customized steel formworks; and sixthly, joint concrete is poured, vibrated and maintained. The construction speed is increased, the process is simple, the construction efficiency is high, and the influence on the surrounding water body can be reduced to the maximum extent.
本发明涉及一种装配式系梁吊装施工方法,步骤一:系梁施工现场预制;步骤二:系梁现场养护与成品保护;步骤三:墩柱桩头钢筋调整;步骤四:系梁现场吊装施工;步骤五:墩柱与系梁节点钢筋加固与安装,定制钢模板安装固定;步骤六:节点混凝土浇筑振捣与养护。本发明加快施工建造速度,工艺简单,施工效率高,可最大程度减少对周围水体造成影响。
Fabricated straining beam hoisting construction method
一种装配式系梁吊装施工方法
LU LIHENG (author) / GUO HONGYU (author) / CHU ZHAO (author) / XIA XIAOHANG (author) / ZHU PENG (author)
2024-01-12
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
European Patent Office | 2023
|Middle straining beam connection construction method of fabricated pier column
European Patent Office | 2023
|Rapid construction method for fabricated straining beam stand column
European Patent Office | 2023
|Replaceable fabricated anti-seismic pier straining beam and construction method thereof
European Patent Office | 2022
|