Method for laying three fields under long and narrow land parcels
The invention provides a method for laying three fields under a long and narrow land parcel, which belongs to the technical field of constructional engineering and comprises the steps of building a reinforcing steel bar processing plant, longitudinally laying a mixing station production area, building a precast beam production area, building a living area and reserving a shortcut. According to the method, three fields are arranged under the long and narrow terrain, compared with a conventional scheme, the existing terrain and foundation conditions can be utilized at the maximum efficiency, the characterization area needed by temporary construction is reduced, a large amount of characterization and demolition cost is saved, the soil body of the existing highway roadbed generally tends to be stable, and the bearing capacity of the soil body serving as a structural foundation can meet the requirement; and the foundation treatment expenditure is reduced.
本发明提出了一种在狭长地块下布设三场的方法,属于建筑工程技术领域,包括建设钢筋加工厂,纵向布设拌和站生产区,建设预制梁生产区,建设生活区,预留便道。本方法在狭长地形下布设三场,和常规方案相比,可以最大效率的利用现有的地形和地基条件,减少临建所需的征迁面积,节约大量的征拆费用,既有高速路基的土体一般的趋于稳定,作为结构基础的承载力能够满足要求,减少地基处理的支出。
Method for laying three fields under long and narrow land parcels
The invention provides a method for laying three fields under a long and narrow land parcel, which belongs to the technical field of constructional engineering and comprises the steps of building a reinforcing steel bar processing plant, longitudinally laying a mixing station production area, building a precast beam production area, building a living area and reserving a shortcut. According to the method, three fields are arranged under the long and narrow terrain, compared with a conventional scheme, the existing terrain and foundation conditions can be utilized at the maximum efficiency, the characterization area needed by temporary construction is reduced, a large amount of characterization and demolition cost is saved, the soil body of the existing highway roadbed generally tends to be stable, and the bearing capacity of the soil body serving as a structural foundation can meet the requirement; and the foundation treatment expenditure is reduced.
本发明提出了一种在狭长地块下布设三场的方法,属于建筑工程技术领域,包括建设钢筋加工厂,纵向布设拌和站生产区,建设预制梁生产区,建设生活区,预留便道。本方法在狭长地形下布设三场,和常规方案相比,可以最大效率的利用现有的地形和地基条件,减少临建所需的征迁面积,节约大量的征拆费用,既有高速路基的土体一般的趋于稳定,作为结构基础的承载力能够满足要求,减少地基处理的支出。
Method for laying three fields under long and narrow land parcels
一种在狭长地块下布设三场的方法
CHE ZHIXIN (author) / LIU JIANXUN (author) / BI SHIBO (author) / LI CHAO (author) / ZHANG JUAN (author) / JIANG FENGQING (author) / ZHANG CHANGXUAN (author) / YANG CHAO (author) / JIANG LANG (author) / ZHANG JINWANG (author)
2024-02-20
Patent
Electronic Resource
Chinese
The "Improved Parcels of Land" Project
British Library Conference Proceedings | 1983
|The Planned Habitat: HLMs, SICAP, Improved Parcels of Land
British Library Conference Proceedings | 1983
|European Patent Office | 2024
|Risk management and control system for organic polluted land parcels and application method
European Patent Office | 2022