Fabricated concrete elevator shaft and construction method thereof
The invention discloses an assembly type concrete elevator shaft and a construction method thereof. The construction method of the concrete elevator shaft comprises the steps that an installation area of the assembly type concrete elevator shaft is measured and drawn; a plurality of stand columns are installed around the installation area at intervals; providing a plurality of hoistway units; a plurality of installation cavities are formed in the hoistway unit, wherein the number of the installation cavities is the same as that of the stand columns. A plurality of well units are sequentially hoisted and stacked in the mounting area, and the multiple stand columns penetrate through the multiple mounting cavities in a one-to-one correspondence mode; a gap is formed between each mounting cavity and the corresponding stand column; grouting materials are poured into the gaps so as to seal the gaps; and a well lid is installed above the shaft unit located on the topmost portion, and construction of the assembly type concrete elevator shaft is completed. According to the fabricated concrete elevator shaft, the time consumed for mounting the shaft unit is shortened, the construction period is shortened, the safety is improved, and the structural stability of the fabricated concrete elevator shaft is improved.
本发明公开了一种装配式混凝土电梯井及其施工方法,混凝土电梯井的施工方法包括:测量并绘制装配式混凝土电梯井的安装区域;环绕所述安装区域间隔安装多根立柱;提供多个井道单元;其中,所述井道单元上形成有与所述立柱数量一致的多个安装腔;将多个井道单元依次吊装并层叠于所述安装区域,且使多个所述立柱一一对应地穿过多个所述安装腔;其中,所述安装腔与其对应的所述立柱之间形成有间隙;向各所述间隙内浇筑灌浆料以将各所述间隙封闭;在位于最顶部的所述井道单元的上方安装井盖,所述装配式混凝土电梯井施工完成。本发明减少了安装井道单元的消耗的时间,缩短了工期,提高了安全性,并且提高了装配式混凝土电梯井的结构稳定性。
Fabricated concrete elevator shaft and construction method thereof
The invention discloses an assembly type concrete elevator shaft and a construction method thereof. The construction method of the concrete elevator shaft comprises the steps that an installation area of the assembly type concrete elevator shaft is measured and drawn; a plurality of stand columns are installed around the installation area at intervals; providing a plurality of hoistway units; a plurality of installation cavities are formed in the hoistway unit, wherein the number of the installation cavities is the same as that of the stand columns. A plurality of well units are sequentially hoisted and stacked in the mounting area, and the multiple stand columns penetrate through the multiple mounting cavities in a one-to-one correspondence mode; a gap is formed between each mounting cavity and the corresponding stand column; grouting materials are poured into the gaps so as to seal the gaps; and a well lid is installed above the shaft unit located on the topmost portion, and construction of the assembly type concrete elevator shaft is completed. According to the fabricated concrete elevator shaft, the time consumed for mounting the shaft unit is shortened, the construction period is shortened, the safety is improved, and the structural stability of the fabricated concrete elevator shaft is improved.
本发明公开了一种装配式混凝土电梯井及其施工方法,混凝土电梯井的施工方法包括:测量并绘制装配式混凝土电梯井的安装区域;环绕所述安装区域间隔安装多根立柱;提供多个井道单元;其中,所述井道单元上形成有与所述立柱数量一致的多个安装腔;将多个井道单元依次吊装并层叠于所述安装区域,且使多个所述立柱一一对应地穿过多个所述安装腔;其中,所述安装腔与其对应的所述立柱之间形成有间隙;向各所述间隙内浇筑灌浆料以将各所述间隙封闭;在位于最顶部的所述井道单元的上方安装井盖,所述装配式混凝土电梯井施工完成。本发明减少了安装井道单元的消耗的时间,缩短了工期,提高了安全性,并且提高了装配式混凝土电梯井的结构稳定性。
Fabricated concrete elevator shaft and construction method thereof
装配式混凝土电梯井及其施工方法
ZHANG YI (author) / LI KAIYUAN (author) / LIN DUANTING (author) / GE BIN (author) / YANG JINGXI (author) / WEI JIAYING (author)
2024-03-15
Patent
Electronic Resource
Chinese
Fabricated concrete elevator shaft and assembling method thereof
European Patent Office | 2023
|Fabricated concrete elevator shaft and assembling method thereof
European Patent Office | 2021
|Fabricated elevator shaft construction equipment and using method
European Patent Office | 2024
|