Construction method for different-direction washboard road in automobile test field
The invention relates to a construction method for a different-direction washboard road in an automobile test field. The construction method comprises the following steps: S1, data preparation; s2, template processing; s3, measuring and setting out; s4, arranging reinforcing meshes; s5, template installation; s6, concrete forming; s7, construction joints are arranged; s8, preserving; the step S6 of concrete forming further comprises the following steps: S6.1, concrete pouring; s6.2, vibrating the concrete; and S6.3, out-phase washboard road wave crest shaping is conducted, specifically, after concrete pouring is completed, a scraping bar is used for shaping, during shaping, the scraping bar takes the line type of the tops of the left and right side formworks as a track, the top face of the concrete is scraped smoothly, and the scraping bar needs to be tightly attached to the tops of the left and right formworks. After the method is constructed and formed, the surface of the bulge is smooth, the curve is smooth, no break point exists, and the appearance quality is good; the construction method is simple, convenient, high in speed and beneficial to construction production organization, and the construction period is effectively shortened.
一种汽车试验场异向搓板路施工方法,包括以下步骤:S1数据准备;S2模板加工;S3测量放样;S4钢筋网片布设;S5模板安装;S6混凝土成型;S7施工缝布设;S8养生;其中,S6混凝土成型还包括以下步骤:S6.1混凝土浇筑;S6.2混凝土振捣;S6.3异相搓板路波峰塑形:混凝土浇筑完成后使用刮杠塑型,塑型时刮杠以左右侧模顶部线型为轨道,对混凝土顶面顺势刮平,刮杠要紧贴左右模板顶部。该方法施工成型后,凸起表面光滑,曲线顺滑、无折点,外观质量好;且施工方法简便、速度快、有利于施工生产组织,有效缩短工期。
Construction method for different-direction washboard road in automobile test field
The invention relates to a construction method for a different-direction washboard road in an automobile test field. The construction method comprises the following steps: S1, data preparation; s2, template processing; s3, measuring and setting out; s4, arranging reinforcing meshes; s5, template installation; s6, concrete forming; s7, construction joints are arranged; s8, preserving; the step S6 of concrete forming further comprises the following steps: S6.1, concrete pouring; s6.2, vibrating the concrete; and S6.3, out-phase washboard road wave crest shaping is conducted, specifically, after concrete pouring is completed, a scraping bar is used for shaping, during shaping, the scraping bar takes the line type of the tops of the left and right side formworks as a track, the top face of the concrete is scraped smoothly, and the scraping bar needs to be tightly attached to the tops of the left and right formworks. After the method is constructed and formed, the surface of the bulge is smooth, the curve is smooth, no break point exists, and the appearance quality is good; the construction method is simple, convenient, high in speed and beneficial to construction production organization, and the construction period is effectively shortened.
一种汽车试验场异向搓板路施工方法,包括以下步骤:S1数据准备;S2模板加工;S3测量放样;S4钢筋网片布设;S5模板安装;S6混凝土成型;S7施工缝布设;S8养生;其中,S6混凝土成型还包括以下步骤:S6.1混凝土浇筑;S6.2混凝土振捣;S6.3异相搓板路波峰塑形:混凝土浇筑完成后使用刮杠塑型,塑型时刮杠以左右侧模顶部线型为轨道,对混凝土顶面顺势刮平,刮杠要紧贴左右模板顶部。该方法施工成型后,凸起表面光滑,曲线顺滑、无折点,外观质量好;且施工方法简便、速度快、有利于施工生产组织,有效缩短工期。
Construction method for different-direction washboard road in automobile test field
汽车试验场异向搓板路施工方法
SHI ZHIWANG (author) / TANG ZHILI (author) / XU BINCHAO (author) / LIU XIYOU (author) / SHEN JINTIAN (author) / GUAN XIN (author) / YU ZIYANG (author) / WANG AOZHAN (author)
2024-03-22
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
WASHBOARD ROAD SURFACE RECOGNITION METHOD AND APPARATUS, MEDIUM, AND CONTROLLER
European Patent Office | 2023
|Washboard type cement concrete pavement and construction method
European Patent Office | 2021
|Physical Modeling of the Washboard Effect on Unpaved Roads
Springer Verlag | 2021
|