Method for hoisting underground diaphragm wall reinforcement cage under low clearance
The invention discloses a low-clearance underground diaphragm wall reinforcement cage hoisting method, and relates to the technical field of subway station construction, and the method comprises the following steps: S1, manufacturing a segmental reinforcement cage; s2, segmental reinforcement cage hoisting; s3, the sectional reinforcement cage is put into a groove; s4, the sectional reinforcement cages are connected; and S5, the modes of hoisting, groove entering and connecting of the sectional reinforcement cage are repeated till connection of the whole reinforcement cage is completed. By means of the method for segmenting the whole reinforcement cage, the problem that in actual construction, due to the complex field environment and insufficient clearance height, a conventional method cannot be adopted for construction for hoisting of the low-clearance reinforcement cage is solved.
本发明公开了一种低净空下地连墙钢筋笼吊装的方法,涉及地铁车站施工技术领域,包括如下步骤,S1:分节钢筋笼制作;S2:分节钢筋笼吊装;S3:分节钢筋笼入槽;S4:分节钢筋笼连接;S5:重复上述分节钢筋笼吊装、入槽以及连接的方式,直至完成整体钢筋笼的连接。本发明通过对整体钢筋笼进行分节的方法,解决实际施工中因现场环境复杂,净空高度不足,不能采用常规方法进行施工的低净空钢筋笼吊装问题。
Method for hoisting underground diaphragm wall reinforcement cage under low clearance
The invention discloses a low-clearance underground diaphragm wall reinforcement cage hoisting method, and relates to the technical field of subway station construction, and the method comprises the following steps: S1, manufacturing a segmental reinforcement cage; s2, segmental reinforcement cage hoisting; s3, the sectional reinforcement cage is put into a groove; s4, the sectional reinforcement cages are connected; and S5, the modes of hoisting, groove entering and connecting of the sectional reinforcement cage are repeated till connection of the whole reinforcement cage is completed. By means of the method for segmenting the whole reinforcement cage, the problem that in actual construction, due to the complex field environment and insufficient clearance height, a conventional method cannot be adopted for construction for hoisting of the low-clearance reinforcement cage is solved.
本发明公开了一种低净空下地连墙钢筋笼吊装的方法,涉及地铁车站施工技术领域,包括如下步骤,S1:分节钢筋笼制作;S2:分节钢筋笼吊装;S3:分节钢筋笼入槽;S4:分节钢筋笼连接;S5:重复上述分节钢筋笼吊装、入槽以及连接的方式,直至完成整体钢筋笼的连接。本发明通过对整体钢筋笼进行分节的方法,解决实际施工中因现场环境复杂,净空高度不足,不能采用常规方法进行施工的低净空钢筋笼吊装问题。
Method for hoisting underground diaphragm wall reinforcement cage under low clearance
一种低净空下地连墙钢筋笼吊装的方法
NIU JUNWEI (author) / WANG XIAOJUN (author) / HUANG LEI (author) / GOU WENBIN (author) / SHAO WEIGUO (author) / YANG KUN (author) / LI DONGMEI (author) / DENG HAICHAO (author) / YIN SHAOBO (author) / CHEN TAOFEI (author)
2024-03-26
Patent
Electronic Resource
Chinese
Underground diaphragm wall reinforcement cage hoisting method
European Patent Office | 2021
|Sectional hoisting connection method for underground diaphragm wall reinforcement cage
European Patent Office | 2024
|European Patent Office | 2024
|European Patent Office | 2023
|Hoisting construction method for reinforcement cage of special-shaped underground diaphragm wall
European Patent Office | 2022
|