Pile sinking construction method for tubular pile in water photovoltaic area
The invention provides a pile sinking construction method for an overwater photovoltaic area pipe pile, and relates to the field of overwater pipe pile sinking. The method comprises the following steps: S1, hoisting two connected buoys into water; s2, the two ends, in the length direction, of the buoy are positioned through a GPS, and positioning piles are driven in so that the buoy can be fixed; s3, the distance between every two pipe piles is marked on the buoy; s4, the first pipe pile is subjected to pile sinking through a positioning mechanism arranged on the buoy; s5, the positioning mechanism is moved to the position where the next pipe pile needs to be subjected to pile sinking, and pile sinking is conducted on the next pipe pile through the positioning mechanism again; and S6, the step S5 is repeated, and pile sinking is conducted on the pipe piles one by one. The construction method has the effect of improving the construction efficiency.
本申请提供了一种水上光伏区管桩的沉桩施工方法,涉及水上管桩沉桩领域。其包括以下步骤:S1:将两根相互连接的浮筒吊入至水中;S2:采用GPS对浮筒沿长度方向上的两端进行定位,并打入定位桩,以对浮筒进行固定;S3:在浮筒上标记每根管桩之间的间距;S4:利用设于浮筒上的定位机构,对第一根管桩进行沉桩;S5:将定位机构移动至下一根管桩需要沉桩的位置,并再次利用定位机构,对下一根管桩进行沉桩;S6:重复步骤S5,逐根对管桩进行沉桩。本申请具有提高施工效率的效果。
Pile sinking construction method for tubular pile in water photovoltaic area
The invention provides a pile sinking construction method for an overwater photovoltaic area pipe pile, and relates to the field of overwater pipe pile sinking. The method comprises the following steps: S1, hoisting two connected buoys into water; s2, the two ends, in the length direction, of the buoy are positioned through a GPS, and positioning piles are driven in so that the buoy can be fixed; s3, the distance between every two pipe piles is marked on the buoy; s4, the first pipe pile is subjected to pile sinking through a positioning mechanism arranged on the buoy; s5, the positioning mechanism is moved to the position where the next pipe pile needs to be subjected to pile sinking, and pile sinking is conducted on the next pipe pile through the positioning mechanism again; and S6, the step S5 is repeated, and pile sinking is conducted on the pipe piles one by one. The construction method has the effect of improving the construction efficiency.
本申请提供了一种水上光伏区管桩的沉桩施工方法,涉及水上管桩沉桩领域。其包括以下步骤:S1:将两根相互连接的浮筒吊入至水中;S2:采用GPS对浮筒沿长度方向上的两端进行定位,并打入定位桩,以对浮筒进行固定;S3:在浮筒上标记每根管桩之间的间距;S4:利用设于浮筒上的定位机构,对第一根管桩进行沉桩;S5:将定位机构移动至下一根管桩需要沉桩的位置,并再次利用定位机构,对下一根管桩进行沉桩;S6:重复步骤S5,逐根对管桩进行沉桩。本申请具有提高施工效率的效果。
Pile sinking construction method for tubular pile in water photovoltaic area
一种水上光伏区管桩的沉桩施工方法
ZHOU XIANG (author) / XIONG ZHIBING (author) / ZHOU YAN (author) / LYU YUANLU (author) / WANG DONG (author) / ZHENG FANGXIN (author)
2024-04-05
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Offshore pile sinking construction method for concrete tubular pile