Construction method based on PHC prefabricated pipe pile and cast-in-situ bored pile under complex stratum
The invention relates to the technical field of civil construction, in particular to a construction method based on a PHC prefabricated pipe pile and a cast-in-situ bored pile under a complex stratum. The method comprises the following steps: S1, on-site investigation and design: carrying out detailed on-site investigation on a construction area; the method is suitable for pile foundation construction under various complex stratums, construction tasks can be efficiently completed in the environment with variable geological conditions and large soil property differences, through reasonable construction organization and equipment configuration, the construction efficiency is improved, the construction period is shortened, through real-time monitoring and quality control, the safety risk in the construction process is reduced, and the construction period is shortened. According to the construction method, the safety of constructors is guaranteed, meanwhile, through strict quality detection and acceptance, the stability of the construction quality of the pile foundation is guaranteed, the safety performance and the service life of a project are improved, pollution such as noise, vibration and dust generated in the construction process is small, and the ecological environment of a construction site is protected.
本发明涉及土建施工技术领域,尤其涉及一种基于复杂地层下PHC预制管桩和钻孔灌注桩的施工方法。本发明包括以下步骤:S1:现场勘察与设计,包括对施工区域进行详细的现场勘察。本发明适用于各种复杂地层下的桩基施工,能够在地质条件多变、土壤性质差异大的环境下高效完成施工任务,且通过合理的施工组织和设备配置,提高了施工效率,缩短了工期,并且通过实时监测和质量控制,降低了施工过程中的安全风险,保证了施工人员的人身安全,同时通过严格的质量检测与验收,确保了桩基施工质量的稳定性,提高了工程的安全性能和使用寿命,并在施工过程中产生的噪音、振动和尘土等污染较小,有利于保护施工现场的生态环境。
Construction method based on PHC prefabricated pipe pile and cast-in-situ bored pile under complex stratum
The invention relates to the technical field of civil construction, in particular to a construction method based on a PHC prefabricated pipe pile and a cast-in-situ bored pile under a complex stratum. The method comprises the following steps: S1, on-site investigation and design: carrying out detailed on-site investigation on a construction area; the method is suitable for pile foundation construction under various complex stratums, construction tasks can be efficiently completed in the environment with variable geological conditions and large soil property differences, through reasonable construction organization and equipment configuration, the construction efficiency is improved, the construction period is shortened, through real-time monitoring and quality control, the safety risk in the construction process is reduced, and the construction period is shortened. According to the construction method, the safety of constructors is guaranteed, meanwhile, through strict quality detection and acceptance, the stability of the construction quality of the pile foundation is guaranteed, the safety performance and the service life of a project are improved, pollution such as noise, vibration and dust generated in the construction process is small, and the ecological environment of a construction site is protected.
本发明涉及土建施工技术领域,尤其涉及一种基于复杂地层下PHC预制管桩和钻孔灌注桩的施工方法。本发明包括以下步骤:S1:现场勘察与设计,包括对施工区域进行详细的现场勘察。本发明适用于各种复杂地层下的桩基施工,能够在地质条件多变、土壤性质差异大的环境下高效完成施工任务,且通过合理的施工组织和设备配置,提高了施工效率,缩短了工期,并且通过实时监测和质量控制,降低了施工过程中的安全风险,保证了施工人员的人身安全,同时通过严格的质量检测与验收,确保了桩基施工质量的稳定性,提高了工程的安全性能和使用寿命,并在施工过程中产生的噪音、振动和尘土等污染较小,有利于保护施工现场的生态环境。
Construction method based on PHC prefabricated pipe pile and cast-in-situ bored pile under complex stratum
一种基于复杂地层下PHC预制管桩和钻孔灌注桩的施工方法
ZHANG WENMING (author) / FU XIAOFENG (author) / YANG CHAO (author) / LI HAILI (author) / WU KEJIA (author) / WANG YUFEI (author) / QIU CHEN (author) / YANG QI (author) / WU JIANXIONG (author) / HOU SHUAIFEI (author)
2024-05-17
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Cast-in-situ bored pile construction method under poor stratum
European Patent Office | 2024
|Karst stratum cast-in-situ bored pile construction method
European Patent Office | 2020
|Soft soil stratum cast-in-situ bored pile construction device
European Patent Office | 2024
|Cast-in-situ bored pile construction process suitable for rock stratum area
European Patent Office | 2021
|