Bridge pier column creeping formwork construction system and construction method thereof
The invention provides a bridge pier column creeping formwork construction system and a construction method thereof. The bridge pier column creeping formwork construction system comprises a crawler, a guide frame, a construction elevator and a formwork system. The crawl device is mounted on a constructed bridge pier column and can move up and down along the bridge pier column; the guide frame is mounted on the crawl device and can be driven by the crawl device to move up and down along the bridge pier column; the template system is mounted on the crawl device by virtue of self weight and can be driven by the crawl device to move up and down along the bridge pier column; the construction hoist comprises a construction hoist operation platform and an annular lifting point frame, the annular lifting point frame is installed at the top end of the guide frame, the construction hoist operation platform is hoisted on the annular lifting point frame through a steel wire rope, and the construction hoist operation platform can ascend and descend along the constructed bridge pier column and the guide frame. According to the bridge pier column creeping formwork construction system and the construction method thereof, the construction progress of a pier can be ensured, the construction cost can be saved, the construction efficiency can be improved, and the construction labor intensity can be reduced.
本发明提供一种桥梁墩柱爬模施工系统及其施工方法,该桥梁墩柱爬模施工系统包括爬行器、导向架、施工升降机、模板系统;爬行器安装在已施工完成的桥梁墩柱上,可沿桥梁墩柱上下运动;导向架安装在爬行器上,可由爬行器带动沿桥梁墩柱上下运动;模板系统靠自重安装在爬行器上,可由爬行器带动沿桥梁墩柱上下运动;施工升降机包括施工升降机操作平台和环状吊点架,环状吊点架安装在导向架顶端,施工升降机操作平台通过钢丝绳吊装在环状吊点架上,施工升降机操作平台可沿已经施工完成的桥梁墩柱和导向架进行上下升降运动。本发明的桥梁墩柱爬模施工系统及其施工方法可确保桥墩施工进度、有利于节约施工成本、提高施工效率、有利于降低施工劳动强度。
Bridge pier column creeping formwork construction system and construction method thereof
The invention provides a bridge pier column creeping formwork construction system and a construction method thereof. The bridge pier column creeping formwork construction system comprises a crawler, a guide frame, a construction elevator and a formwork system. The crawl device is mounted on a constructed bridge pier column and can move up and down along the bridge pier column; the guide frame is mounted on the crawl device and can be driven by the crawl device to move up and down along the bridge pier column; the template system is mounted on the crawl device by virtue of self weight and can be driven by the crawl device to move up and down along the bridge pier column; the construction hoist comprises a construction hoist operation platform and an annular lifting point frame, the annular lifting point frame is installed at the top end of the guide frame, the construction hoist operation platform is hoisted on the annular lifting point frame through a steel wire rope, and the construction hoist operation platform can ascend and descend along the constructed bridge pier column and the guide frame. According to the bridge pier column creeping formwork construction system and the construction method thereof, the construction progress of a pier can be ensured, the construction cost can be saved, the construction efficiency can be improved, and the construction labor intensity can be reduced.
本发明提供一种桥梁墩柱爬模施工系统及其施工方法,该桥梁墩柱爬模施工系统包括爬行器、导向架、施工升降机、模板系统;爬行器安装在已施工完成的桥梁墩柱上,可沿桥梁墩柱上下运动;导向架安装在爬行器上,可由爬行器带动沿桥梁墩柱上下运动;模板系统靠自重安装在爬行器上,可由爬行器带动沿桥梁墩柱上下运动;施工升降机包括施工升降机操作平台和环状吊点架,环状吊点架安装在导向架顶端,施工升降机操作平台通过钢丝绳吊装在环状吊点架上,施工升降机操作平台可沿已经施工完成的桥梁墩柱和导向架进行上下升降运动。本发明的桥梁墩柱爬模施工系统及其施工方法可确保桥墩施工进度、有利于节约施工成本、提高施工效率、有利于降低施工劳动强度。
Bridge pier column creeping formwork construction system and construction method thereof
一种桥梁墩柱爬模施工系统及其施工方法
LUO LIANG (author) / LIU ZHIHUA (author) / LI LONG (author) / YANG KE (author) / QIN MINGQING (author) / ZHUO SHENGSHENG (author) / LI TIANJU (author)
2024-05-21
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Bridge abutment high pier hydraulic creeping formwork construction method
European Patent Office | 2023
|Expressway bridge high pier hydraulic creeping formwork construction method
European Patent Office | 2024
|Formwork and construction method for bridge formwork turnover pier column construction
European Patent Office | 2023
|European Patent Office | 2023
|