Segmented prefabrication flow construction method for coke oven hearth column
The invention discloses a segmented prefabrication flow construction method for coke oven hearth columns. Comprising the steps of hearth column segmented design, coke oven cushion layer pouring, column reinforcement cage prefabrication, column typified formwork prefabrication, bottom plate bottom layer steel bar binding, bottom plate surface layer steel bar binding, column reinforcement cage hoisting, bottom plate pouring maintenance, column root scabbling, column typified formwork hoisting, column concrete pouring and the like. According to the method, after the furnace bed columns are prefabricated and formed in a segmented mode, the furnace bed columns and the foundation are connected into a whole through cast-in-place, flow construction can be achieved while the design connection strength is completely met, the construction efficiency can be greatly improved, the construction period is shortened, and quality control and inspection are more convenient through the prefabricated column reinforcement cages and the prefabricated shaping formworks.
本发明公开了一种焦炉炉床柱的分部预制流水施工方法,包括炉床柱分部设计、焦炉垫层浇筑、柱钢筋笼预制、柱定型模板预制、底板底层钢筋绑扎、底板面层钢筋绑扎、柱钢筋笼吊装、底板浇筑养护、柱根凿毛、柱定型模板吊装、柱混凝土浇筑等步骤。本发明在分部预制成型炉床柱后,通过现浇将炉床柱与基础连接成整体,在完全满足设计连接强度的同时,可实现流水施工,能够大大提高施工效率,缩短施工周期,预制的柱钢筋笼和定型模板更加便于质量控制和检查。
Segmented prefabrication flow construction method for coke oven hearth column
The invention discloses a segmented prefabrication flow construction method for coke oven hearth columns. Comprising the steps of hearth column segmented design, coke oven cushion layer pouring, column reinforcement cage prefabrication, column typified formwork prefabrication, bottom plate bottom layer steel bar binding, bottom plate surface layer steel bar binding, column reinforcement cage hoisting, bottom plate pouring maintenance, column root scabbling, column typified formwork hoisting, column concrete pouring and the like. According to the method, after the furnace bed columns are prefabricated and formed in a segmented mode, the furnace bed columns and the foundation are connected into a whole through cast-in-place, flow construction can be achieved while the design connection strength is completely met, the construction efficiency can be greatly improved, the construction period is shortened, and quality control and inspection are more convenient through the prefabricated column reinforcement cages and the prefabricated shaping formworks.
本发明公开了一种焦炉炉床柱的分部预制流水施工方法,包括炉床柱分部设计、焦炉垫层浇筑、柱钢筋笼预制、柱定型模板预制、底板底层钢筋绑扎、底板面层钢筋绑扎、柱钢筋笼吊装、底板浇筑养护、柱根凿毛、柱定型模板吊装、柱混凝土浇筑等步骤。本发明在分部预制成型炉床柱后,通过现浇将炉床柱与基础连接成整体,在完全满足设计连接强度的同时,可实现流水施工,能够大大提高施工效率,缩短施工周期,预制的柱钢筋笼和定型模板更加便于质量控制和检查。
Segmented prefabrication flow construction method for coke oven hearth column
一种焦炉炉床柱的分部预制流水施工方法
SONG MINGHAO (author)
2024-05-28
Patent
Electronic Resource
Chinese
Combined coke oven hearth column and construction method thereof
European Patent Office | 2023
|COKE OVEN TEMPORARY SUPERSTRUCTURE AND CONSTRUCTION METHOD OF COKE OVEN
European Patent Office | 2015
|Engineering Index Backfile | 1906
|Pier column segmental prefabrication and aerial splicing construction method
European Patent Office | 2024
|