A platform for research: civil engineering, architecture and urbanism
Turnover shaped tower crane foundation steel platform and construction method thereof
The invention relates to a turnover shaped tower crane foundation steel platform and a construction method thereof.The turnover shaped tower crane foundation steel platform comprises a pile foundation, a pile foundation reinforcing assembly, a steel platform assembly, a foundation section and a fixing assembly, the pile foundation is reinforced through the pile foundation reinforcing assembly, and the steel platform assembly is detachably installed at the top of the pile foundation; and the basic section is arranged at the bottom of the tower crane supporting leg and is fixed with the steel platform assembly through a fixing assembly. The steel platform is a steel reinforced concrete steel platform, is connected with the steel pipe piles through flanges, and is safe and reliable; the steel platform can be manufactured in factories and assembled on site, disassembly is fast, and time is saved; the steel platform and the steel pipe piles can be recycled, and cost is low compared with a traditional tower crane foundation.
本发明是一种可周转的定型化塔吊基础钢平台及其施工方法,包括桩基础、桩基加固组件、钢平台组件、基础节、固定组件,桩基础通过桩基加固组件加固,钢平台组件可拆卸安装在桩基础顶部,基础节设置在塔吊支腿底部并与钢平台组件之间通过固定组件固定。本发明为“型钢混凝土”钢平台,与钢管桩采用法兰连接,安全可靠;钢平台可工厂制作、现场组装,拆卸快捷、节省时间;钢平台、钢管桩可以周转使用,相对传统塔吊基础费用低。
Turnover shaped tower crane foundation steel platform and construction method thereof
The invention relates to a turnover shaped tower crane foundation steel platform and a construction method thereof.The turnover shaped tower crane foundation steel platform comprises a pile foundation, a pile foundation reinforcing assembly, a steel platform assembly, a foundation section and a fixing assembly, the pile foundation is reinforced through the pile foundation reinforcing assembly, and the steel platform assembly is detachably installed at the top of the pile foundation; and the basic section is arranged at the bottom of the tower crane supporting leg and is fixed with the steel platform assembly through a fixing assembly. The steel platform is a steel reinforced concrete steel platform, is connected with the steel pipe piles through flanges, and is safe and reliable; the steel platform can be manufactured in factories and assembled on site, disassembly is fast, and time is saved; the steel platform and the steel pipe piles can be recycled, and cost is low compared with a traditional tower crane foundation.
本发明是一种可周转的定型化塔吊基础钢平台及其施工方法,包括桩基础、桩基加固组件、钢平台组件、基础节、固定组件,桩基础通过桩基加固组件加固,钢平台组件可拆卸安装在桩基础顶部,基础节设置在塔吊支腿底部并与钢平台组件之间通过固定组件固定。本发明为“型钢混凝土”钢平台,与钢管桩采用法兰连接,安全可靠;钢平台可工厂制作、现场组装,拆卸快捷、节省时间;钢平台、钢管桩可以周转使用,相对传统塔吊基础费用低。
Turnover shaped tower crane foundation steel platform and construction method thereof
一种可周转的定型化塔吊基础钢平台及其施工方法
HE WENLONG (author) / CHEN JINHUI (author) / HU JIE (author) / XIE LIXIANG (author) / CAO JUNQI (author)
2024-05-28
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Turnover assembly type universal tower crane foundation and construction method thereof
European Patent Office | 2022
|Construction method of turnover assembly type tower crane foundation
European Patent Office | 2024
|Construction method of special-shaped tower crane foundation
European Patent Office | 2021
|