A platform for research: civil engineering, architecture and urbanism
Hoisting equipment and hoisting process for concrete double-column canopy side plate of railway station
The invention relates to hoisting equipment and a hoisting process for a concrete double-column canopy side plate of a railway station, the equipment comprises a main beam, two front supports, two middle supports and two rear supports, and the front supports, the middle supports and the rear supports are symmetrically arranged on the main beam in sequence from front to back; the middle support is telescopically arranged on the main beam, a forward track is arranged in the extending direction of the main beam, a movable vertical track is arranged on the side, away from the main beam, of the forward track, and a movable crane carriage is arranged on the side, away from the forward track, of the vertical track. According to the method, transportation or rail hoisting can be carried out without line dismantling or by adopting a special rail car, the method is not limited by an offline roadbed, and cooperation of an offline construction unit is not needed.
本发明涉及一种铁路客站混凝土双柱雨棚边板的吊装设备及吊装工艺,该设备包括:主梁、前支撑、中支撑和后支撑,所述前支撑、所述中支撑和所述后支撑的数量均为两个,且按照由前到后的顺序依次对称设置在所述主梁上,所述中支撑可收缩设置在所述主梁上,沿所述主梁延伸方向设置有顺向轨道,所述顺向轨道远离所述主梁的一侧设置有可移动的垂向轨道,所述垂向轨道远离所述顺向轨道的一侧设置有可移动的起重小车。本发明可以实现不进行线路拆除或是采用专用轨道车就可以运输或进行轨道吊装,且不受线下路基的制约,不需要线下施工单位的配合。
Hoisting equipment and hoisting process for concrete double-column canopy side plate of railway station
The invention relates to hoisting equipment and a hoisting process for a concrete double-column canopy side plate of a railway station, the equipment comprises a main beam, two front supports, two middle supports and two rear supports, and the front supports, the middle supports and the rear supports are symmetrically arranged on the main beam in sequence from front to back; the middle support is telescopically arranged on the main beam, a forward track is arranged in the extending direction of the main beam, a movable vertical track is arranged on the side, away from the main beam, of the forward track, and a movable crane carriage is arranged on the side, away from the forward track, of the vertical track. According to the method, transportation or rail hoisting can be carried out without line dismantling or by adopting a special rail car, the method is not limited by an offline roadbed, and cooperation of an offline construction unit is not needed.
本发明涉及一种铁路客站混凝土双柱雨棚边板的吊装设备及吊装工艺,该设备包括:主梁、前支撑、中支撑和后支撑,所述前支撑、所述中支撑和所述后支撑的数量均为两个,且按照由前到后的顺序依次对称设置在所述主梁上,所述中支撑可收缩设置在所述主梁上,沿所述主梁延伸方向设置有顺向轨道,所述顺向轨道远离所述主梁的一侧设置有可移动的垂向轨道,所述垂向轨道远离所述顺向轨道的一侧设置有可移动的起重小车。本发明可以实现不进行线路拆除或是采用专用轨道车就可以运输或进行轨道吊装,且不受线下路基的制约,不需要线下施工单位的配合。
Hoisting equipment and hoisting process for concrete double-column canopy side plate of railway station
一种铁路客站混凝土双柱雨棚边板的吊装设备及吊装工艺
CHEN YUEPING (author) / MEI HONGLIANG (author) / ZHOU DAXING (author) / LIU PENG (author) / WEN KAI (author) / QIAN ZENGZHI (author) / FANG HONGWEI (author) / JIANG JIAQI (author) / ZHAO FENGQING (author) / LI RONGXIN (author)
2024-06-04
Patent
Electronic Resource
Chinese
European Patent Office | 2024
|Integrated hoisting equipment and process for concrete double-column canopy of railway station
European Patent Office | 2024
|European Patent Office | 2024
|European Patent Office | 2020
|