Construction method for removing mud cake of cast-in-place pile
The invention relates to the technical field of cast-in-place pile mud cakes, and discloses a cast-in-place pile mud cake removing construction method which comprises the steps that (1) drilling construction is conducted in a soil layer to form a soil layer hole; (2) drilling construction is conducted in the rock stratum to form rock stratum holes, the soil layer holes and the rock stratum holes are communicated up and down to form cast-in-place pile holes, and the inner side walls of the cast-in-place pile holes are covered with mud walls; (3) a sand bailing hopper is tripped into the cast-in-place pile hole for bailing rock slag, a drill rod is connected to the sand bailing hopper, a power structure for driving the sand bailing hopper to rotate is connected to the drill rod, a mud brushing device is arranged on the sand bailing hopper, and a plurality of steel wire brushes are arranged on the mud brushing device; in the process that the sand bailing hopper descends into the cast-in-place pile hole, the rotating state is kept, the mud brushing device synchronously moves along with the sand bailing hopper and keeps the rotating state, and the multiple steel wire brushes brush the mud cake wall and brush the mud cake wall off from the inner side wall of the cast-in-place pile hole till the sand bailing hopper moves to the bottom of the cast-in-place pile hole; and (4) the bailing hopper is lifted out from bottom to top, the bailing hopper and the wall brushing device are washed with clear water, and the wall brushing device is detached from the bailing hopper.
本发明涉及灌注桩泥皮的技术领域,公开了清除灌注桩泥皮施工方法,包括:1)、在土层中钻进施工形成土层孔;2)、在岩层中钻进施工形成岩层孔,土层孔与岩层孔上下连通形成灌注桩孔,灌注桩孔的内侧壁覆盖有泥皮壁;3)、利用捞砂斗下入灌注桩孔中捞取岩渣,捞砂斗连接有钻杆,钻杆上连接有驱动捞砂斗转动的动力结构,捞砂斗上设有刷泥器,刷泥器上设有多个钢丝刷;捞砂斗下入灌注桩孔的过程中,保持转动状态,刷泥器随着捞砂斗同步移动且保持转动状态,多个钢丝刷刷动泥皮壁,将泥皮壁从灌注桩孔的内侧壁上刷落,直至捞砂斗移动至灌注桩孔的底部;4)、自下而上提升捞砂斗至提出,利用清水冲洗捞砂斗及刷壁器,将刷壁器从捞砂斗上拆除下来。
Construction method for removing mud cake of cast-in-place pile
The invention relates to the technical field of cast-in-place pile mud cakes, and discloses a cast-in-place pile mud cake removing construction method which comprises the steps that (1) drilling construction is conducted in a soil layer to form a soil layer hole; (2) drilling construction is conducted in the rock stratum to form rock stratum holes, the soil layer holes and the rock stratum holes are communicated up and down to form cast-in-place pile holes, and the inner side walls of the cast-in-place pile holes are covered with mud walls; (3) a sand bailing hopper is tripped into the cast-in-place pile hole for bailing rock slag, a drill rod is connected to the sand bailing hopper, a power structure for driving the sand bailing hopper to rotate is connected to the drill rod, a mud brushing device is arranged on the sand bailing hopper, and a plurality of steel wire brushes are arranged on the mud brushing device; in the process that the sand bailing hopper descends into the cast-in-place pile hole, the rotating state is kept, the mud brushing device synchronously moves along with the sand bailing hopper and keeps the rotating state, and the multiple steel wire brushes brush the mud cake wall and brush the mud cake wall off from the inner side wall of the cast-in-place pile hole till the sand bailing hopper moves to the bottom of the cast-in-place pile hole; and (4) the bailing hopper is lifted out from bottom to top, the bailing hopper and the wall brushing device are washed with clear water, and the wall brushing device is detached from the bailing hopper.
本发明涉及灌注桩泥皮的技术领域,公开了清除灌注桩泥皮施工方法,包括:1)、在土层中钻进施工形成土层孔;2)、在岩层中钻进施工形成岩层孔,土层孔与岩层孔上下连通形成灌注桩孔,灌注桩孔的内侧壁覆盖有泥皮壁;3)、利用捞砂斗下入灌注桩孔中捞取岩渣,捞砂斗连接有钻杆,钻杆上连接有驱动捞砂斗转动的动力结构,捞砂斗上设有刷泥器,刷泥器上设有多个钢丝刷;捞砂斗下入灌注桩孔的过程中,保持转动状态,刷泥器随着捞砂斗同步移动且保持转动状态,多个钢丝刷刷动泥皮壁,将泥皮壁从灌注桩孔的内侧壁上刷落,直至捞砂斗移动至灌注桩孔的底部;4)、自下而上提升捞砂斗至提出,利用清水冲洗捞砂斗及刷壁器,将刷壁器从捞砂斗上拆除下来。
Construction method for removing mud cake of cast-in-place pile
清除灌注桩泥皮施工方法
GUO QIUPING (author) / WANG WEIJIE (author) / LI CHANGHAI (author) / ZENG XIANGWU (author) / HE ZHUORONG (author)
2024-06-07
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method for removing reinforced concrete cast-in-place pile body
European Patent Office | 2020
|Construction method for post-grouting solidified mud cake on pile side of cast-in-place pile
European Patent Office | 2024
|CAST-IN-PLACE PILE AND CONSTRUCTION METHOD OF CAST-IN-PLACE PILE
European Patent Office | 2023
|European Patent Office | 2024
|