Semi-reversed-sequence construction method of ultrahigh closed concrete reservoir
The invention discloses a semi-reversed-order construction method of an ultrahigh closed concrete reservoir, which comprises the following steps of: erecting a main body bracket, binding reinforcing steel bars of a reservoir wall structure, erecting a formwork, binding reinforcing steel bars of a top plate, erecting the formwork, and simultaneously pouring concrete on the reservoir wall and the top plate, so that the conventional reservoir wall construction procedure is broken, and the construction efficiency is improved. Compared with a conventional pool wall construction process which has the defects of long construction period, high cost and high safety risk, the construction process is simplified, erection and disassembly of a temporary operation frame are reduced, and the construction cost is greatly reduced; and all procedures are completed at a time, the progress is fast, and therefore the problems that a conventional pool wall construction procedure is long in construction period, high in cost and large in safety risk are solved.
本发明公开了一种超高封闭式混凝土蓄水池的半逆序施工方法,通过搭设主体支架、其次进行池壁结构的钢筋绑扎、支模、随后对顶板进行钢筋绑扎、支模,再同时对池壁、顶板进行混凝土浇筑,打破了常规的池壁施工工序,相对于常规池壁施工工序工期长、成本高、安全风险大的缺陷,使得本发明相对于常规的池壁施工工序,本发明简化了施工工序,减少了临时操作架的搭拆,大大降低施工成本低;且所有工序一次性完成,进度快较快,从而解决了常规的池壁施工工序工期长、成本高、安全风险大的问题。
Semi-reversed-sequence construction method of ultrahigh closed concrete reservoir
The invention discloses a semi-reversed-order construction method of an ultrahigh closed concrete reservoir, which comprises the following steps of: erecting a main body bracket, binding reinforcing steel bars of a reservoir wall structure, erecting a formwork, binding reinforcing steel bars of a top plate, erecting the formwork, and simultaneously pouring concrete on the reservoir wall and the top plate, so that the conventional reservoir wall construction procedure is broken, and the construction efficiency is improved. Compared with a conventional pool wall construction process which has the defects of long construction period, high cost and high safety risk, the construction process is simplified, erection and disassembly of a temporary operation frame are reduced, and the construction cost is greatly reduced; and all procedures are completed at a time, the progress is fast, and therefore the problems that a conventional pool wall construction procedure is long in construction period, high in cost and large in safety risk are solved.
本发明公开了一种超高封闭式混凝土蓄水池的半逆序施工方法,通过搭设主体支架、其次进行池壁结构的钢筋绑扎、支模、随后对顶板进行钢筋绑扎、支模,再同时对池壁、顶板进行混凝土浇筑,打破了常规的池壁施工工序,相对于常规池壁施工工序工期长、成本高、安全风险大的缺陷,使得本发明相对于常规的池壁施工工序,本发明简化了施工工序,减少了临时操作架的搭拆,大大降低施工成本低;且所有工序一次性完成,进度快较快,从而解决了常规的池壁施工工序工期长、成本高、安全风险大的问题。
Semi-reversed-sequence construction method of ultrahigh closed concrete reservoir
一种超高封闭式混凝土蓄水池的半逆序施工方法
HUANG RUIXIONG (author) / WANG WEI (author)
2024-07-09
Patent
Electronic Resource
Chinese
Concrete construction method for shear wall of ultrahigh closed structure
European Patent Office | 2024
|Construction method of ultrahigh independent concrete column
European Patent Office | 2023
|Grouting reversed-sequence construction method for fabricated vertical component
European Patent Office | 2021
|Construction method and construction template for ultrahigh oblique concrete column
European Patent Office | 2016
|Prestressed concrete reservoir construction
Engineering Index Backfile | 1954
|